ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Mini Split voltage
by Garemaret - 06/21/24 04:53 AM
Strobing LEDs
by Anovalight - 06/20/24 03:16 AM
Stuff that happens after we leave
by HotLine1 - 06/17/24 03:53 PM
photocell requirement for metal halide ballasts
by gfretwell - 06/17/24 01:44 PM
Commercial lift stations
by triple - 06/09/24 05:23 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
2 members (Scott35, gfretwell), 154 guests, and 10 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Joined: Jul 2012
Posts: 9
K
New Member
Hello,

I wanted to inquire if it is possible to estimate available electrical capacity in an electrical distribution system based on only peak demand information available. For e.g. if an 800A, 347/600V, 3-phase electrical service has a peak demand of 175kW, would it be safe to assume the following calculation to estimate available electrical capacity at unity power factor:

800A x 0.8 = 640A (max. loading)
175kW = 600V x A x 1.732 i.e. A = 168A
Available capacity would be 640A - 168A = 472A.

Would the estimation of available capacity change if there are 600V - 208V step-down transformers downstream of the electrical distribution system?

Thank you.

Joined: Apr 2002
Posts: 7,386
Likes: 7
Member
You will have to calc the existing loads on each of the transformers.


John
Joined: Mar 2006
Posts: 82
B
Member
The code now allows this. You have to provide at least 12 months of peak demand data from the utility bills.


Link Copied to Clipboard
Powered by UBB.threads™ PHP Forum Software 7.7.5