Plug terminals
Who's Online Now
0 registered members (), 14 guests, and 19 spiders.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Light Pole Grounding #219506
08/18/18 07:42 AM
08/18/18 07:42 AM
M
Mosfet74  Offline OP
New Member
Joined: Aug 2018
Posts: 1
Australia
Am helping a client with a light pole design for Canada. They only supply the pole, so no luminaire, hood, or wiring. There’s been some conflicting discussion about grounding terminals required to be supplied on the pole to ground the luminaire when installed onsite. The pole currently has a primary grounding terminal at the base. In practice, does the pole itself need an additional terminal at the top for the luminaire to be bonded to, or is the grounding wire connected from the luminaire down to the primary terminal considered sufficient?

Thanks!

Tools for Electricians:
Re: Light Pole Grounding [Re: Mosfet74] #219512
08/20/18 04:34 PM
08/20/18 04:34 PM
HotLine1  Offline

Member
Joined: Apr 2002
Posts: 7,051
Brick, NJ USA
The luminaire is grounded via the GEC that is part of te branch circuit feeding the lighting.

The pole is bonded via the GEC at a lug accessable via the handhole.

That is USA, and NEC, Canada may be the same.


John
Re: Light Pole Grounding [Re: Mosfet74] #219533
08/24/18 05:21 PM
08/24/18 05:21 PM
S
sparky  Offline
Member
Joined: Oct 2000
Posts: 5,371
IIRC, there was some past debate about this, apparently the jist orbited around weather a light pole could be considered a structure ,and then have art 225 follow suit with GEC's and all that.

I'm not sure where that went , but i do know metallic poles 1000' away from the serving facility are best having some bond to the 'crete they sit upon , usually the 4 threaded rods ,man made electrode

And no , i don't have a code ref , sorry..

Last edited by HotLine1; 08/25/18 02:43 PM. Reason: Ooops wrong post
Re: Light Pole Grounding [Re: Mosfet74] #219534
08/24/18 06:38 PM
08/24/18 06:38 PM
HotLine1  Offline

Member
Joined: Apr 2002
Posts: 7,051
Brick, NJ USA
Well, now lets go to the ‘spec’, tediously written, and most times drawn within the plans. Some spec a 8’ rod, cadwelded to #6 or 4 cu, up into the pole base. Some spec a 10’ rod, or some spec 20’ min., #x rebar, with #4 Cu.

Thinking back, one that jumps to mind is site lighting for a new bank. Spec was 10’ rod, cadweld, #4 Cu. No sweat, yje EC did his thing & insp was OK. Poles arrive, I just was driving by, ‘sparky’ had the pole on his shoulder, all 15’ of it. Turns out the poles is the fixture schedule were FIBERGLASS!!! Duh,


John
Re: Light Pole Grounding [Re: Mosfet74] #219564
08/28/18 08:07 AM
08/28/18 08:07 AM
G
ghost307  Offline
Member
Joined: May 2005
Posts: 963
Chicago Illinois USA
I don't know if they ever revised it, but at one time the local Code for one of the cities in Ohio included a detail of how to attach the grounding conductor to a lug on a fiberglass pole.

Double-duh.


Ghost307

Featured:

2017 Master Electrician Exam Preparation Combos
2017 NEC Electrician
Exam Prep Combos:
Master / Journeyman

 

Member Spotlight
renosteinke
renosteinke
Blue Collar Country
Posts: 5,316
Joined: January 2005
Show All Member Profiles 
Top Posters(30 Days)
Popular Topics(Views)
252,281 Are you busy
189,229 Re: Forum
178,915 Need opinion
Powered by UBB.threads™ PHP Forum Software 7.6.1
(Release build 20180101)
Page Time: 0.020s Queries: 15 (0.004s) Memory: 0.9690 MB (Peak: 1.1097 MB) Zlib enabled. Server Time: 2018-12-19 01:58:47 UTC