ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat Box
Recent Posts
Lock-down Thread
by NORCAL - 02/26/21 07:28 AM
Northern Tool Recalls Powerhorse Generators
by Admin - 02/25/21 09:49 PM
You will never guess
by gfretwell - 02/25/21 07:48 PM
New tool
by SMOKEYBOB - 02/15/21 04:59 PM
New in the Gallery:
Facebook follies, bad wiring
FPE in Germany pt.2
Who's Online Now
1 registered members (Scott35), 15 guests, and 18 spiders.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Automating Manual Gen Transfer Swtich... #204272 11/25/11 02:03 PM
Joined: Nov 2011
Posts: 1
J
johnmixdecn Offline OP
New Member
Hi all. I have a setup with a diesel genset. This genset feeds a 3 phase panel (120/120/120). This panel has 4 double breakers, each feed a single phase panel, each of which has a manual transfer switch that switchs the panel between line power and the 3 phase gen panel. This has worked well for years.

What im looking to do is to automate this. Installing 3 auto transfer switchs is beyond my budget.

What im thinking is I will write a program that runs on a dedicated PC (on battery backup of course) that will watch the incoming power, and when we lose power, or a even lose a single phase...it will start and warm up the genset. Then it will wait a few minutes then flip each transfer switch over. I have writen a similar program for a smaller application that was in a communications shed in the woods. It worked great.

This is where my question comes in. Would it violate code in any way to have an electric actuator push/pull the handle of the transfer switchs from "Line" to "Gen"? I cant see how it would since this is external from any electrics and is doing this same thing as a human fliping the switch.

--John

Work Gear for Electricians and the Trades
Re: Automating Manual Gen Transfer Swtich... [Re: johnmixdecn] #204273 11/25/11 03:20 PM
Joined: Jul 2004
Posts: 9,569
G
gfretwell Offline
Member
When you change a manual transfer switch to automatic (any way you do it) you do bring in the requirement that the generator now must be capable of maintaining the entire connected load.
Does your program do load management?
Other than that you might bump into 110.3(B) about using equipment the way the manufacturer's instructions specify.



Greg Fretwell

Featured:

2020 National Electrical Code
2020 National Electrical
Code (NEC)

* * * * * * *

2020 Master Electrician Exam Preparation Combos
2020 NEC Electrician
Exam Prep Combos:
Master / Journeyman

 

Member Spotlight
SafetyWired
SafetyWired
Pa, USA
Posts: 44
Joined: July 2013
Show All Member Profiles 
Top Posters(30 Days)
Popular Topics(Views)
275,411 Are you busy
209,304 Re: Forum
196,593 Need opinion
Powered by UBB.threads™ PHP Forum Software 7.7.3