ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
Shout Box
Recent Posts
334.80 and fire caulk
by gfretwell. 06/21/18 11:35 AM
Calling all Non-US members!! (Non-US only)
by HotLine1. 06/13/18 01:50 PM
GE Lighting Recalls LED Tube Lamps
by Admin. 06/12/18 09:32 PM
Ketra Recalls Recessed Downlights
by Admin. 06/12/18 09:17 PM
diazed fuses
by Texas_Ranger. 06/11/18 07:31 AM
New in the Gallery:
Plug terminals
Housebilding DIY wiring
Who's Online Now
0 registered members (), 33 guests, and 22 spiders.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Page 1 of 3 1 2 3
Mounting service gear before brick. #163291
05/05/07 05:04 PM
05/05/07 05:04 PM
T
Trick440  Offline OP
Member
Joined: Aug 2005
Posts: 248
Waterford, MI, USA
Do you guys do anything special when you mount your service equipment to a building that has not been bricked yet?

What we do is stack some 2x4 secure them to the building so it gets us away from the building enough to clear the brick. So its just 2 horizonal rows of stacked 2x4. We haven't had a problem with this... until lately.

2 different brick crews think its ok just to rip our service gear off the wall, brick behind it, then just let the service gear hang from the pvc.

Its not like we can wait for brick to hang our equipment. They need power in these buildings.

So I'm wondering what you guys do. Only thing I can think of is taking a brick and knocking the bricky over the head with it.


Shake n Bake
Work Gear for Electricians and the Trades
Re: Mounting service gear before brick. [Re: Trick440] #163294
05/05/07 06:21 PM
05/05/07 06:21 PM
L
LK  Offline
Member
Joined: Jan 2003
Posts: 1,429
New Jersey
Temp service, then when the building is ready, install new service. Or have the GC schedule an electrician to remove and replace, (Good Luck on that one)But there is alwayt the chance, you may have a GC with all his brain cells firing and he will work with you.
We had a few nice fires in town over the years, from contractors pulling services away from the building.

Re: Mounting service gear before brick. [Re: LK] #163295
05/05/07 06:54 PM
05/05/07 06:54 PM
electure  Offline

Member
Joined: Dec 2000
Posts: 4,268
Fullerton, CA USA
This type of thing is just why power isn't released by the AHJ until buildings are completed.
I'm amazed that they'll let you power up a service, much less let some brick yahoo rip it off the wall.

Re: Mounting service gear before brick. [Re: electure] #163296
05/05/07 07:26 PM
05/05/07 07:26 PM
L
LK  Offline
Member
Joined: Jan 2003
Posts: 1,429
New Jersey
Scott,
One GC said to me, what do you expect me to do, tell the owner he has to pay for that too, I would not have any work, what do you think all the other contractors do, they don't pay an electrician to do it, they just rip it off the building, and put one of the straps back on, what do you think, it's rocket science to put a strap on.
Then when you explain the dangers, they reply, that a crock, it's a no win, when your dealing with some of these guys, most of them have no formal training, in any of the trades, they letter a truck, print business cards, and bingo instant GC.
In my state all they need to do is register and make a payment, no testing to see if their qualified, just turn them loose. It might be a good idea, to make them attend a CEU class on safety, It's clear they are still not operating on a full 8 when it comes to safety.

I am sorry if I sound a bit rasp on this issue, but we have eniough problem keeping our image as a safe industry, with all the hacks, we don't need the sdditional burden of GC's tearing up our work and leaving it in an unsafe condition.

Last edited by LK; 05/05/07 07:45 PM.
Re: Mounting service gear before brick. [Re: LK] #163300
05/05/07 09:18 PM
05/05/07 09:18 PM
F
Fred  Offline
Member
Joined: Apr 2001
Posts: 449
Straughn, IN 47387
I mount meterbase/service equipment before brick all of the time. I fabricate a mounting bracket from 1/4" x 2" angle iron and bolt it to the plywood/OSB. It stands the equipment off of the sheeting 4-1/2". This allows the brick to be layed up behind the equipment leaving a gap to be caulked when they are finished.

Re: Mounting service gear before brick. [Re: Fred] #163303
05/05/07 09:46 PM
05/05/07 09:46 PM
L
LK  Offline
Member
Joined: Jan 2003
Posts: 1,429
New Jersey
Originally Posted by Fred
I mount meterbase/service equipment before brick all of the time. I fabricate a mounting bracket from 1/4" x 2" angle iron and bolt it to the plywood/OSB. It stands the equipment off of the sheeting 4-1/2". This allows the brick to be layed up behind the equipment leaving a gap to be caulked when they are finished.


Our uitlity would not accept that, even as a temporary service, only the published specs, in the utility installation handbook are approved.
I tried that stunt once, and the utility cut the service. I can see their issue, a powered up service before the equiment base construction is complete, is asking for an accident.

Last edited by LK; 05/05/07 09:54 PM.
Re: Mounting service gear before brick. [Re: LK] #163304
05/05/07 10:20 PM
05/05/07 10:20 PM
C
Celtic  Offline
Member
Joined: Feb 2005
Posts: 361
NJ
Originally Posted by LK
Scott,
One GC said to me, what do you expect me to do, tell the owner he has to pay for that too, ...


I've run into that situation a few times.
I gave the GC 2 choices:
1 - Pay me for the temp and maint. of same
2 - Run YOUR job on generators, and I'll have nothing to do with it.

Some comprehend #1 and go with my "suggestion".
Some go with #2 and have "issues".
One such job resulted in EVERY sub suppling their own portable generators. A very loud job to say the least ....until ALL the generators got stolen one night (along with bunches of tools, gang boxes, etc). Could have been angry neighbors...who knows?

Another job...this was a comedy....large diesel genny "ran out of fuel"....the genius who went to get more fuel - ran out of fuel in the truck...LMAO.

I had nothing to do with these "issues".


~~ CELTIC ~~
...-= NJ =-...
Re: Mounting service gear before brick. [Re: LK] #163307
05/05/07 11:32 PM
05/05/07 11:32 PM
F
Fred  Offline
Member
Joined: Apr 2001
Posts: 449
Straughn, IN 47387
LK, What do you see as a safety issue? The equipment is permanently mounted. The mounting base is complete, it is a steel bracket permanently fastened to the structure. This not a "stunt", it is an engineer approved mounting system. Would you suggest a service be de-energized when masonry is repointed? Same situation. I would like to see PoCo installation specs that prohibit this installation.

Re: Mounting service gear before brick. [Re: Fred] #163364
05/07/07 01:41 AM
05/07/07 01:41 AM
Samurai  Offline
Member
Joined: May 2007
Posts: 46
Fl.
most General contractors started out as those guys who rip services off buildings, not as electricians. I agree with most of the others (you don't have to put up with disrespectful GCs)
I gotta side with the temporary "pole"/generator crowd on this one - you want power before the house is completed? - that's how it's gonna BE - putting a service up twice is a service call, and it may be financially more prudent to consider alternative power methods before using destructive force on a completed install. (which YOU had to have immediately)
charge him for reinstalling the service
if he doesn't learn you'll be saved the hassle of working with him again


Re: Mounting service gear before brick. [Re: Samurai] #163365
05/07/07 03:22 AM
05/07/07 03:22 AM
E
e57  Offline
Member
Joined: May 2003
Posts: 2,876
S.F.,CA USA
Why not just do it by the numbers and have the area where the panel is going to be bricked first? (old panel in old location) Then put up the new one in the new location as the bricklayers move on. Rip out the old one. OH, I forgot bulldogs can't herd cats.... wink


Mark Heller
"Well - I oughta....." -Jackie Gleason
Page 1 of 3 1 2 3

Featured:

2017 Master Electrician Exam Preparation Combos
2017 NEC Electrician
Exam Prep Combos:
Master / Journeyman

 

Member Spotlight
electure
electure
Fullerton, CA USA
Posts: 4,268
Joined: December 2000
Show All Member Profiles 
Top Posters(30 Days)
twh 5
Popular Topics(Views)
247,711 Are you busy
185,020 Re: Forum
174,346 Need opinion
Powered by UBB.threads™ PHP Forum Software 7.6.1
(Release build 20180101)
Page Time: 0.026s Queries: 16 (0.005s) Memory: 1.0298 MB (Peak: 1.2112 MB) Zlib enabled. Server Time: 2018-06-25 00:12:56 UTC