4 x 500 MCM + 1 X 3/0 CU pull - somewhere in Maine! More photos if you want. Source is Cat generator - 140' away. 3 phase 480 - 1600 A. Total of 4 - 4" RMC, each as noted above. Application - paving plant.
Be gentle! We're out here in the woods!
Grov ![[Linked Image]](https://www.electrical-contractor.net/Forum/Images/500_MCM_Pull.JPG)
|
|
|
|
Joined: Nov 2006
Posts: 32
Member
|
Nice wire stands, I see you have the lube ready. wheres the back hoe wire puller at 
|
|
|
|
Joined: Jan 2005
Posts: 109
Member
|
Actually didn't use the backhoe this time - see the forklift in the distance? Limited to 5' at a time - the height of the Gen enclosure door.
I remember another pull - excavator used to position pulley above pipe - rope to pickup truck......
|
|
|
|
Joined: Jun 2005
Posts: 821
Member
|
That's awesome!
I don't normally work with the big stuff, but I'll remember this technique next time I do.
|
|
|
|
Joined: Jul 2006
Posts: 272
Member
|
Was that little bucket of lube enough for the pull? Seems like you would need a heck-of-a-lot more than that in the pic...I could picture someone right at the stub up, guiding the wires into the conduit with a big vat of polywater right next to him. Using generous amounts of it for the entire length of the pull. So how were yall set up? Was any of my speculation the case?
The more polywater the better! 
Luke Clarke Electrical Planner for TVA.
|
|
|
|
Joined: Jan 2005
Posts: 109
Member
|
I used 3 buckets of lube for the pull - almost a bucket per pull. 3 helpers guiding wire off the spools and into the switchgear. I was at the stub-up, laying on a 2x10, waterproof gloves, doing the final guide into the pipe and slathering the lube. Continuous lube for the entire pull.