Just wondering if anyone is familiar with PPL and could shed some insight on an upcoming project.

We are looking at a project that would upgrade 11 townhouse buildings in one community from a 2-Position 200A (each townhouse unit having a 100A service) to a 3-Position Meter Center.

The 3rd Meter would be for a condo association subpanel, to service some lighting loads and receptacles for Verizon fiber equipment. It would be a NEMA 3r 4Ckt MLO 125A rated panel with 3-20 A breakers installed- installed right next to the meter center and fed from a 2-Pole 60A breaker in the meter center.

My question is - what is the procedure for moving the meters from the existing meter center to the new meter center.

Since no feeders are being upgraded we are looking at a total downtime of maybe 1-2 hours per building, while we de-terminate and pull down the meter center and put up and re-terminate the new center.

The only unknown is getting the existing meters back in.

Any insight on this would be appreciated.

Thanks!