... Okay,...it's dopey question time,..
When looking over plans for pricing out wiring a new house/addition,..etc,..when the builder/GC says for me to "allow for $5,000.00 for fixtures"..what exactly does that mean?? He says "give them(the H.O.) a certain allowance".. Do I include that into the price?? I'm lost with this terminology..How does it effect me as the installer.. [Linked Image] [Linked Image]