From the "Don't Try This At Home" department:

Once had a really long pull of 500MCM's thru a really ugly conduit run, and the Greenlee tugger wouldn't tug any more (wire half way in). So my boss, great guy that he is, got us another Greenlee tugger. Not a super tugger. So what could we do? We used 2 tuggers in-line and finished the pull.

I chained both tuggers to a 4" piece of heavy sprinkler pipe, and mounted that on unistrut standoff's to the concrete deck with about 6 sets of anchors. Pull went OK, but we were overstressing the rope a bit. I had arranged the entire assembly so i could handle the rope from behind a CMU wall (thru a doorway), just in case it all came loose, or the rope broke.

Note to anyone else dumb enough to try something like this: ONE AND ONLY ONE turn of rope around the back tugger's capstan. It was actually fairly easy to control.

Not the smartest thing I've ever done, but it worked.

Radar


There are 10 types of people. Those who know binary, and those who don't.