We have a client we did a job for that wants to expand his facility. The original building was very technical in nature and done design build on a fast track schedule. He has contacted the original GC and MEP subs to do a TI addition to some space they did not originally develop. There is one catch. They do not want to get a permit. The reason I have heard is they do not want the problems with the city they had the first time. Weather we do the job or not is not my decision. That responsibility is upper managements territory. While they have not officially said no, they are leaning heavily on not participating.
I believe I know most of the repercussions that can arise from doing something like this but I wanted to get your opinions. I have to go to a scope meeting Monday morning and try to convince them to do it right so we can do the job for them.
Any thoughts?