Hi,
Thanks for the reply. I know that I could make a few extra dollars on material but the owner has already agreed to let a supply company provide the material in a container for 6 units at a time.

The owner is doing another 110 units right after this one is done and has plans to develop several subdivisions. I am in a booming area and they are building on any available ground. I could see alot of additional work from this. I know that you hear that all the time from the owner or gc but what they say has no effect on my decision other than the fact that when that day comes its a bridge i will cross then. If i never see any additional work then no big deal.

I am allowing 8 hours per unit which includes trim.

8 hours per unit is 880 hrs total work.

-regards

mustang