I saw an installation inside a school building yesterday involving two transformers of the same rating located in the same room. The GECs from each transformer were installed in the same raceway up to the steel. Is this an acceptable installation method? I do not know the answer, so any help is appreciated.

In the same school, another room and another transformer. The GEC was run in the slab (in a raceway) out of the room across the hall and then up the wall to steel in the room across the hall. What do you think of this installation.

Pierre