okay i give up...i know that somewhere it's in the nec, but i don't know where to find the article that tells us that dead wiring must be removed, or safed off properly. i'm fighting with an owens corning basement finishing contractor about having dead ckts. behind the walls.
Top
2017 / 2014 NEC & Related Books and Study Guides
#99642 - 08/23/06 07:14 PM Re: de-energized wiring
renosteinke Offline
Cat Servant
Member
Registered: 01/22/05
Posts: 5316
Loc: Blue Collar Country
Lots of luck finding it! While there are secions dealing with abandoned phone, data, and cable TV wires.... the NEC is silent on power wires!

I don't like it, but there it is.
Top
#99643 - 08/25/06 09:21 PM Re: de-energized wiring
hedlok Offline
Junior Member
Registered: 03/25/06
Posts: 8
Loc: pa.
after much searching i found the article in the nj fire code...we (electrical) are responsible for enforcing parts of other subcodes here in nj. the fire official stered me to the right article in his code.
Top
#99644 - 08/26/06 03:45 AM Re: de-energized wiring
jwhite Offline
Member
Registered: 12/01/05
Posts: 64
Loc: Trenton, NC, USA
I have had inspectors make us remove unused wires, but never if they were behind finished walls. Or are you saying they had the chance to remove them before the walls were covered?
Top
#99645 - 08/26/06 07:38 PM Re: de-energized wiring
hedlok Offline
Junior Member
Registered: 03/25/06
Posts: 8
Loc: pa.
on the rough i found the cables and j boxes behind studs set off 6" from the basement walls, they were live at the time of the rough. i explained to the contractor that they were to be removed..he did not comply, he said that the "owens-corning" system was "accessible"....and the rest is history
Top
#99646 - 08/27/06 05:10 PM Re: de-energized wiring
barf Offline
Junior Member
Registered: 04/07/06
Posts: 8
Loc: nys
Take out the old stuff,, as per 110.3(A)(8)!
Top
#99647 - 08/27/06 05:27 PM Re: de-energized wiring
iwire Offline
Moderator
Registered: 01/05/03
Posts: 4391
Loc: North Attleboro, MA USA
I hope you kidding 'barf'.

110.3(A)(8) is not a blanket requirement to pull out old wiring.

Quote:
110.3 Examination, Identification, Installation, and Use of Equipment.

(A) Examination. In judging equipment, considerations such as the following shall be evaluated:

(8) Other factors that contribute to the practical safeguarding of persons using or likely to come in contact with the equipment


As a matter of fact 110.3(A) is about installation and use of equipment.

Abandoned equipment is not being used or installed.
_________________________
Bob Badger
Construction & Maintenance Electrician
Massachusetts
Top

Member Spotlight
Member Since: 11/17/00
Posts: 2232
New in the Gallery:
SE cable question
Featured:

2017 NEC and Related
2017 NEC
Now Available!

Shout Box


Who's Online
0 registered (), 43 Guests and 10 Spiders online.
Key: Admin, Global Mod, Mod
 
New in the Gallery:
SE cable question
 
Top Posters (30 Days)
Admin 47
HotLine1 43
gfretwell 19
Ruben Rocha 12
Trumpy 9
 
Newest Members
KrmtFrg, Stack, Scotto, Freecrowder, clee512

ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals