The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!

Featured:
   

2017 NEC and Related
2017 NEC
Now Available!

   
Recent Posts
Calling all Non-US members!! (Non-US only)
by aussie240
Yesterday at 02:39 AM
Photo Upload Tutorial
by DanK
12/06/16 11:35 PM
Sprinklered equipment 26-008
by bigpapa
12/02/16 04:24 PM
On Delay Relay with Auto Reset
by Potseal
12/01/16 09:59 AM
Wow, that was close!
by jraef
11/28/16 07:06 PM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 13
HotLine1 9
Texas_Ranger 8
sparkyinak 7
Trumpy 6
Who's Online
0 registered (), 196 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#99556 - 08/14/06 04:07 PM Fire Pump wiring Art 695
Yoopersup Offline
Member

Registered: 03/04/03
Posts: 826
Loc: Michigan
When a Fire pumps Fed from Mulitple sources (Generator- Power Company) the way I read it both sources are required to comply with 695.6 (B) 1 or 2 or 3 . Any input on this Please. Both Generator and Power company sources are remote from Fire Pump control transfer switch & controller.

Top
2014 / 2011 NEC & Related Books and Study Guides
#99557 - 08/14/06 06:06 PM Re: Fire Pump wiring Art 695
George Little Offline
Member

Registered: 01/18/04
Posts: 1492
Loc: Michigan USA
Ernie- I'm far from being the Firepump Guru on this Board but there aren't any exceptions that I read so my answer is yes both supplies must comp[y with 695.6(B) 1 or 2 or 3.

Hey ask easier questions like "What color is a green ground screw?"

See Ya in TC
_________________________
George Little