#99329 - 10/28/04 04:06 AM New Grounding Methods ???
Megawatt Offline
Member
Registered: 03/11/04
Posts: 76
Loc: Lexington,Ky, USA
Just got My 2005 Code Book, looking at some changes, & it seems We are going to have some issues with grounding rebar in concrete.
Does anyone have any ideas on this yet, Would it be possible to have the concrete contractors leave a section stubed out above the pour ?
On jobs where there aren't any conduit runs to be incased, the EC may not be anywhere near the site when the pour occurs.
Also, it looks like Building Steel, Rebar, Metal Waterline etc will ALL be connected now.
Top
2017 / 2014 NEC & Related Books and Study Guides
#99330 - 10/28/04 06:18 AM Re: New Grounding Methods ???
Ryan_J Offline
Moderator
Registered: 08/19/03
Posts: 1374
Loc: West Jordan, Utah, USA
I think what will have to happen is that if the EC isn't on site before or during the pour, the footing contractor will have to stub out a piece of rebar for the EC to tie onto. As far as the building steel, water line, etc., these were already required to be tied together.

I better make sure we're on the same page. You're talking about 250.50, right?

[This message has been edited by Ryan_J (edited 10-28-2004).]
_________________________
Ryan Jackson,
Salt Lake City
Top
#99331 - 10/28/04 06:53 AM Re: New Grounding Methods ???
Megawatt Offline
Member
Registered: 03/11/04
Posts: 76
Loc: Lexington,Ky, USA
I believe so, I don't have My Code book with Me, but I think that is correct.
What do You know about the coated rebar ???
That doesn't require bonding ??
Top
#99332 - 10/28/04 08:58 AM Re: New Grounding Methods ???
Roger Offline
Member
Registered: 05/18/02
Posts: 1716
Loc: N.C.
Coated rebar is commonly used in bridge construction and has no metal contact with the concrete.

I have never seen it used in footers, but doesn't mean it isn't.

Roger
Top
#99333 - 10/28/04 01:08 PM Re: New Grounding Methods ???
Megawatt Offline
Member
Registered: 03/11/04
Posts: 76
Loc: Lexington,Ky, USA
Our Cont Ed Instructor said it may be used more often, After 2005 is adopted, if the cost isn't too prohibitive.
Seems easy enough to just stub up a piece above the pour though....
Top
#99334 - 10/28/04 02:28 PM Re: New Grounding Methods ???
Ryan_J Offline
Moderator
Registered: 08/19/03
Posts: 1374
Loc: West Jordan, Utah, USA
The cost of epoxy coated steel, in my opinion, is never going to be less expensive than simply using normal steel and having to use it as an electrode.
_________________________
Ryan Jackson,
Salt Lake City
Top
#99335 - 10/28/04 04:41 PM Re: New Grounding Methods ???
earlydean Offline
Member
Registered: 12/22/03
Posts: 751
Loc: Griswold, CT, USA
The beauty when using the rebar as a grounding electrode is that the 2 ground rods are no longer required.
Also, just because the 2005 NEC is out, doesn't mean that your town or state has adopted it.
_________________________
Earl
Top
#99336 - 10/29/04 11:23 AM Re: New Grounding Methods ???
CharlieE Offline
Member
Registered: 04/23/04
Posts: 200
Loc: Indianapolis
Now that it is going to be required everywhere . . . eventually. How does Florida do it now? I believe they require the Ufer throughout the state and the concrete contractor just turns up a piece of the rebar in the area of the service. I would like to hear how it's done in Florida now.

- - - - - - - - - - - - - - - - - - - - - - - - - -
Charlie Eldridge, Indianapolis, Utility Power Guy
_________________________
Charlie Eldridge, Indianapolis Utility Power Guy
Top
#99337 - 12/21/04 09:19 PM Re: New Grounding Methods ???
gfretwell Offline


Member
Registered: 07/20/04
Posts: 9036
Loc: Estero,Fl,usa
They turn up a #5 in SW Florida. It comes up into the block cell and they knock a hole so the can get to it (usually sprayed green so it doesn't get poured solid when they do the dowels). The electrician pushes his #4 down from the panel to meet the #5, puts a bronze acorn on it and puts a blank cover over the hole.
_________________________
Greg Fretwell
Top
#99338 - 12/30/04 05:58 AM Re: New Grounding Methods ???
Gary S Offline
Member
Registered: 12/29/04
Posts: 12
Loc: Houston, Texas, USA
It is my opinion that the intent of previous editions of the code was that the rebar system was supposed to be used as a portion of the grounding electrode already. The 2005 change from "If available on the premises" to "that are present at" is simply an effort to more concisely spell out what the intent was. There is nothing new here. We should have been connecting into the rebar system all along.
Top
Page 1 of 4 1 2 3 4 >

Member Spotlight
Member Since: 04/03/02
Posts: 6775
New in the Gallery:
SE cable question
Featured:

2017 NEC and Related
2017 NEC
Now Available!

Shout Box


Who's Online
0 registered (), 55 Guests and 9 Spiders online.
Key: Admin, Global Mod, Mod
 
New in the Gallery:
SE cable question
 
Top Posters (30 Days)
Admin 51
HotLine1 43
gfretwell 17
Trumpy 16
Ruben Rocha 13
 
Newest Members
clee512, Jdscott2005, FAIZAN, Regitest2, sureshazhagai

ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals