The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!

Featured:
   

2017 NEC and Related
2017 NEC
Now Available!

   
Recent Posts
Sprinklered equipment 26-008
by bigpapa
Today at 04:24 PM
On Delay Relay with Auto Reset
by Potseal
Yesterday at 09:59 AM
Wow, that was close!
by jraef
11/28/16 07:06 PM
Earthquake in New Zeeland
by RODALCO
11/27/16 11:25 PM
Calling all Non-US members!! (Non-US only)
by Tjia1981
11/27/16 06:33 AM
New in the Gallery:
12.5A through 0.75mm≤ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 15
HotLine1 10
Texas_Ranger 8
Trumpy 8
sparkyinak 7
Who's Online
0 registered (), 202 Guests and 7 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#90245 - 11/09/04 07:33 AM Hybrid System
Steve T Offline
Member

Registered: 02/14/01
Posts: 312
Loc: Oak Park, IL, USA
An owner of a single family home wants to install wind turbines and solar panels on his roof.

In a nutshell--What would you ask for as the plan reviewer who has to review the electrical portion of the job (not structural support)?

I have come up with:
1)A complete one-line diagram showing all associated equipment.

2)Show the location of all the equipment.

3)Provide Manuf. specs on all equipment.

4)Provide the rating of all OCPD's.

5)Provide dc system voltage of PV output circuit and combined turbine and PV output circuit.

6)Provide a letter from the utility giving their approval of the system.

Top
2014 / 2011 NEC & Related Books and Study Guides
#90246 - 11/09/04 08:47 AM Re: Hybrid System
gfretwell Offline

Member

Registered: 07/20/04
Posts: 9045
Loc: Estero,Fl,usa
Bonding?
_________________________
Greg Fretwell

Top
#90247 - 11/09/04 03:36 PM Re: Hybrid System
Bjarney Offline
Moderator

Registered: 04/10/02
Posts: 2561
Loc: West-Southern Inner-Northeast ...
 
In some areas, typical electrical-standards boilerplate for small PV/inverter installations is IEEE 929, UL 1741 and NEC 690.

Top
#90248 - 11/09/04 06:04 PM Re: Hybrid System
John Steinke Offline
Member

Registered: 04/03/01
Posts: 509
Loc: Reno,Nv., USA
Don't forget a "ladder logic" diagram showing how this mess will be controlled.

Top
#90249 - 11/10/04 06:44 PM Re: Hybrid System
HotLine1 Offline

Member

Registered: 04/03/02
Posts: 6804
Loc: Brick, NJ USA
OK< sunlight resistant cables, wiring, suitable bushings, connectors, raceways, etc.
Sunlight resistant ty-wraps, discos (utility requirement here)

The other AHJ is the solar cell maven, I'll see if he has a op to stop over here next week

John
_________________________
John

Top
#90250 - 11/10/04 06:54 PM Re: Hybrid System
Roger Offline
Member

Registered: 05/18/02
Posts: 1779
Loc: N.C.
If these Wind Turbines, Solar panels, and associated wiring don't comply, what would an inspector do? AS far as the power they produce, there would be no meter to pull or hold hostage.

Roger

Top
#90251 - 11/11/04 05:14 PM Re: Hybrid System
WireWrestler Offline
Member

Registered: 10/29/01
Posts: 43
Loc: Northern IL
We install the same type of systems you are talking about. I assume you are on the ComEd grid. If the systems are to be grid-tied for net metering they must meet the UL1741 spec. mentioned. As far as I know, all of the off the shelf equipment does. I recomend that you go to http://www.bergey.com/ They have the most information and best wind turbines available. We are dealers for them and they are great.
Bob

Top