The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!

Featured:
   

2017 NEC and Related
2017 NEC
Now Available!

   
Recent Posts
Sprinklered equipment 26-008
by bigpapa
12/02/16 04:24 PM
On Delay Relay with Auto Reset
by Potseal
12/01/16 09:59 AM
Wow, that was close!
by jraef
11/28/16 07:06 PM
Earthquake in New Zeeland
by RODALCO
11/27/16 11:25 PM
Calling all Non-US members!! (Non-US only)
by Tjia1981
11/27/16 06:33 AM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 13
HotLine1 9
Texas_Ranger 8
sparkyinak 7
Trumpy 6
Who's Online
1 registered (sparkyinak), 245 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#85728 - 07/31/03 02:43 PM Required additional disconnecting means?
EnergyPlus Offline
Junior Member

Registered: 07/31/03
Posts: 1
Loc: Troy, IL, USA
This is a rather unique situation so please let me set this up correctly.

This is for a Streetscape project where decorative streetlights run down both sides of the street. The lighting circuit is unmetered by the utility and I don't think it is in question. There are 4 duplex recepticals at the base of each light and each half is protected by a GFI Breaker.

The meter and panel structure were installed mid block near the sidewalk(above ground). Property owner changed heart and refused to give easement. Meter was moved 100 feet back from sidewalk to alley and underground feeder ran from meter point to end of block to main street and back to center of block near sidewalk (original location). Electrical panels were mounted in a concrete vault under the sidewalk and is accessible by manhole cover. Electrical panels have 20 - 20 amp circuit breakers and a 300 amp main disconnect. Is an additional disconnect required at the meter?

Who would ever know what it controlled and why would it be necessary? These recepticals are only going to be energized 1 or 2 weekends for festivals. Other times the service will be OFF.

thanks

Top
2014 / 2011 NEC & Related Books and Study Guides
#85729 - 08/01/03 03:23 AM Re: Required additional disconnecting means?
zapped208 Offline
Member

Registered: 02/18/03
Posts: 201
Loc: Somewhere in USA
No disconnect needs to be added. The conductors that go underground to the vault and panel are still service entance conductors, from the meter.
_________________________
Shoot first, apologize later.....maybe

Top



ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals