The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!


2017 NEC and Related
2017 NEC
Now Available!

Recent Posts
Son of Sparky
by HotLine1
Yesterday at 07:43 PM
Speaking of Plugmold ...
by gfretwell
10/17/16 02:37 PM
Broken battery charger? Check for cobwebs!
by gfretwell
10/17/16 02:30 PM
230 or 345 kV transmission lines?
by annemarie1
10/12/16 01:23 PM
Is this a fix or just a bandaid?
by gfretwell
10/10/16 06:49 PM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 11
renosteinke 6
HotLine1 6
ghost307 5
sparky 4
Who's Online
0 registered (), 107 Guests and 7 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#82429 - 11/13/02 09:50 PM Code Clarification Request
Joe Tedesco Offline

Registered: 10/07/00
Posts: 3325
Loc: Boston, Massachusetts USA
Clarification of Code 230-71

I have a question regarding 230-71 (Maximum Number of Disconnects.)

Reguarding the exception on Power Monitor Equipment; Do Power Factor Correction Capacitors fall under this exception, even if it is controlled by a power monitoring controller? I have argued that is doesn't, but if it does I shall hang my head and admit defeat.

Thank you,
Donny Griffith
Joe Tedesco, NEC Consultant

2014 / 2011 NEC & Related Books and Study Guides
#82430 - 11/14/02 02:51 PM Re: Code Clarification Request
sparky Offline

Registered: 10/18/00
Posts: 5545
i recall a similar thread, the focus being a surge suppression unit.....

#82431 - 11/16/02 11:44 PM Re: Code Clarification Request
Jacuzzi Guy Electric Offline

Registered: 10/25/02
Posts: 33
Loc: Dearborn Heights Michigan Unit...
What is the size of the capacitor bank and why would you utilize the service lateral or service drop to connect them? You can only have one svc. Drop Or Lateral and up to six Meter cans and their disconnects. It that what you meant?

#82432 - 11/18/02 04:55 PM Re: Code Clarification Request
sparky Offline

Registered: 10/18/00
Posts: 5545
It would seem that the last sentence of 230.71(A) that addresses power monitoring could apply to a cap bank....

#82433 - 11/18/02 07:57 PM Re: Code Clarification Request
resqcapt19 Offline

Registered: 11/10/00
Posts: 2209
Loc: IL
There is no way that the intent of 230.71 would permit a 7th disconnect for power factor correction capacitors. Power monitoring is exactly that, some type of instrumentation that monitors the power.