ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals

Page 1 of 3 1 2 3 >
Topic Options
Rate This Topic
#7524 - 02/08/02 10:53 PM Some electrical engineers should have to install their plans...
3rd degree Burns Offline
Member
Registered: 02/04/02
Posts: 36
Loc: Dallas, Texas, USA
Another journeyman & I (with 2 helpers) are now into our 4th week of turning a new & empty 80'x30' into the control room of the soon to be largest switch on the biggest trunk (345KV) in Texas. I know they(the utility)are exempt from code but there ARE some strange things, such as using white (as well as green) for phase, but using black for ground. OK...I got over that one. Next, after installing the overhead trays, AC & DC panels, etc., I wire in the requisite 5 rows of the usual cheesy fluorescent fixtures and receptacles according to prints. At this point we still haven't received the panel schedules, but hey.... they show the circuit numbers on the lighting and receptacle prints (AC 43X, AC44X, AC45Y, AC46Y, etc.), and, knowing service will be 240v.(X&Y), I mount both panels (1-42)&(43-84)and terminate the 120v. stuff. This week the panel schedules finally show up...and when I saw how the engineer has arbitrarily choosen to number the circuits according to his idea of the actual number of circuits with no correlation to panel numbers, well........ Example, if the first breaker on the left hand side was a two-pole 240v breaker, one would normally number the first wire #1(X-black) and the red wire below it #3(Y-red). Said engineer instead chooses AC1X and AC1Y. OK.....I can learn to live with that. BUT....I'm running service this coming Monday and I wonder how AM I going to pull FOUR 4/0 THW's for a distance of 150' through a single 2" underground PVC with two 90's ? (from the 200 A. disconnect I installed out by the transfer switch all the way into the control room to my distribution panels). But this IS what the customer calls for...and the plans MUST BE FOLLOWED!!!

[This message has been edited by 3rd degree Burns (edited 02-09-2002).]

[This message has been edited by 3rd degree Burns (edited 02-09-2002).]

[This message has been edited by 3rd degree Burns (edited 02-09-2002).]
Top
Work Gear for Electricians and the Trades
#7525 - 02/09/02 03:51 AM Re: Some electrical engineers should have to install their plans...
sparky Offline
Member
Registered: 10/18/00
Posts: 5303
LOL!, 3rd Deg.........get the pull 1/2 way there, play the 'dope' and ask him how to do it.
Top
#7526 - 02/09/02 09:54 AM Re: Some electrical engineers should have to install their plans...
electure Offline


Member
Registered: 12/24/00
Posts: 4259
Loc: Fullerton, CA USA
Send a Request for Information to the engineer, detailing your problem.
(He'll try to shirk it off, of course)
Then, give them a price to run a properly sized conduit overhead. Make sure you get a signed Change Order before you proceed with the work.
Top
#7527 - 02/09/02 10:10 AM Re: Some electrical engineers should have to install their plans...
resqcapt19 Offline
Member
Registered: 11/10/00
Posts: 2148
Loc: IL
Four 4/0 THWNs or XHHWs will fit in 2" schedule 40 PVC. Are the 90's PVC or rigid? The pull rope will probably cut through the 90's if they are PVC.
Don(resqcapt19)
_________________________
Don(resqcapt19)
Top
#7528 - 02/09/02 03:50 PM Re: Some electrical engineers should have to install their plans...
sparky66wv Offline
Member
Registered: 11/17/00
Posts: 2232
Loc: West Virginia
In a pinch, buy some nylon webbing from a caver or mountain climbing supply, (or any other source if you can find it...) 1" to 1-1/4" wide is good. It will be less likely to cut into the PVC Sweeps.
_________________________
-Virgil
Residential/Commercial Inspector
5 Star Inspections
Member IAEI
Top
#7529 - 02/09/02 04:00 PM Re: Some electrical engineers should have to install their plans...
resqcapt19 Offline
Member
Registered: 11/10/00
Posts: 2148
Loc: IL
Sparky,
In a rope rescue class I was taught that moving nylon straps on any type of pastic was something to avoid. They said there was too much heat build up and the nylon could fail. Of course this was for life safety not pulling wire. I've never tried a nylon strap, but often use rigid 90s in under ground runs. I've also had good luck soaping the pull rope.
Don(resqcapt19)
_________________________
Don(resqcapt19)
Top
#7530 - 02/09/02 04:05 PM Re: Some electrical engineers should have to install their plans...
sparky66wv Offline
Member
Registered: 11/17/00
Posts: 2232
Loc: West Virginia
Hmmm!?!? Allegheny Power uses webbing for UG pulls, mabe it's not Nylon?

What about bonding concerns with the lone GRC sweeps in the middle of PVC runs?

[This message has been edited by sparky66wv (edited 02-09-2002).]
_________________________
-Virgil
Residential/Commercial Inspector
5 Star Inspections
Member IAEI
Top
#7531 - 02/09/02 04:41 PM Re: Some electrical engineers should have to install their plans...
resqcapt19 Offline
Member
Registered: 11/10/00
Posts: 2148
Loc: IL
Sparky,
I've never used them above grade and the code permits them to be unbonded when they are covered with 18" of earth. See Exception #3 to 250.86.
Don(resqcapt19)
_________________________
Don(resqcapt19)
Top
#7532 - 02/09/02 04:45 PM Re: Some electrical engineers should have to install their plans...
Nick Offline
Member
Registered: 08/13/01
Posts: 599
Loc: Riverside, CA
GRC sweeps so not need to be bonded if they are at least 18” underground.

I have found that mule tape works real good. It has footage marks every foot too.
Top
#7533 - 02/09/02 06:52 PM Re: Some electrical engineers should have to install their plans...
resqcapt19 Offline
Member
Registered: 11/10/00
Posts: 2148
Loc: IL
What is "mule" tape.
If I'm pulling anything like that it would be with tugger and the rope that goes with it.
Don(resqcapt19)
_________________________
Don(resqcapt19)
Top
Page 1 of 3 1 2 3 >

Member Spotlight
Member Since: 11/17/00
Posts: 2232
New in the Gallery:
SE cable question
Featured:

2017 NEC and Related
2017 NEC
Now Available!

Shout Box


Who's Online
0 registered (), 51 Guests and 11 Spiders online.
Key: Admin, Global Mod, Mod
 
New in the Gallery:
SE cable question
 
Top Posters (30 Days)
Admin 49
HotLine1 43
gfretwell 18
Ruben Rocha 12
Trumpy 9
 
Newest Members
Freecrowder, clee512, Jdscott2005, FAIZAN, Regitest2

ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals