ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals

Topic Options
Rate This Topic
#7029 - 01/19/02 05:55 PM First in & Last out
sparky Offline
Member
Registered: 10/18/00
Posts: 5303
We are one of the first trades in, to a vacant lot, for temp service.
As such we hear all grandious plans, the carrot is dangeled, handshakes exchange , prospects are solicited, etc.


The Job progresses
cue Good,Bad & Ugly theme....


We are one of the last trades out, the plans have 'evolved', some may be held in contempt, the well's run dry.....

For many of us the latter is repetitive, the signs and symptoms of overall job success or failure is apparent to various degree.
I'm interested in what has held the ear/eye of others in said respect here.
Top
Work Gear for Electricians and the Trades
#7030 - 01/20/02 05:31 AM Re: First in & Last out
electure Offline


Member
Registered: 12/24/00
Posts: 4259
Loc: Fullerton, CA USA
I've attended many pre-job meetings that the GC stated "Requests for Information will have a response within a day". My usual action was to send as many RFI's as I could immediately to clear up discrepancies (better proactive than reactive) before they became problems. They've rarely been answered within a week; some have taken months.

There have been a few occasions where I've submitted alternate lighting/switchgear packages, only to be told "No substitutions, go strictly by the specs". The same people have asked me to value engineer the job halfway through, probably after some "bean counter" actually counted up the "beans".
You can always tell a job's gonna be a Turkey when it sounds like they've got delusions of grandeur
Top
#7031 - 01/20/02 05:59 AM Re: First in & Last out
George Corron Offline
Member
Registered: 05/16/01
Posts: 717
Loc: Lorton, Va USA
Electure,
working for an engineering firm, I can tell you my biggest problem with GC's is usually their response to RFI's. 'course, then at least I have an NCN (Non-compliance Notice)

I thought the "6 phases of a project" were a list, then someone informed me it was supposed to be funny, heck I judge the completion of a project by them, with darned few exceptions. If you haven't heard them, you'll have to wait 'til Tuesday cause it's hanging over my desk, but the last two are:

5) Search for the guilty, punishment of the innocent.

6) Praise and honors for the non-participants.
Like I said, I thought someone had come up with a real good barometer of job progress attitudes.
Top

Member Spotlight
Member Since: 02/23/13
Posts: 204
New in the Gallery:
SE cable question
Featured:

2017 NEC and Related
2017 NEC
Now Available!

Shout Box


Who's Online
1 registered (Admin), 56 Guests and 8 Spiders online.
Key: Admin, Global Mod, Mod
 
New in the Gallery:
SE cable question
 
Top Posters (30 Days)
Admin 47
HotLine1 43
gfretwell 19
Ruben Rocha 12
Trumpy 9
 
Newest Members
KrmtFrg, Stack, Scotto, Freecrowder, clee512

ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals