The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!


2017 NEC and Related
2017 NEC
Now Available!

Recent Posts
Parking lot pole light swap....
by gfretwell
10/24/16 08:46 PM
International Wire Colour Codes
by Tjia1981
10/23/16 12:08 PM
Son of Sparky
by HotLine1
10/20/16 07:43 PM
Speaking of Plugmold ...
by gfretwell
10/17/16 02:37 PM
Broken battery charger? Check for cobwebs!
by gfretwell
10/17/16 02:30 PM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 14
ghost307 7
HotLine1 7
renosteinke 6
Potseal 4
Who's Online
1 registered (Tjia1981), 298 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#40766 - 08/03/04 11:30 AM Outside disco
Big A Offline

Registered: 01/22/03
Posts: 47
Loc: Lynchburg, VA
Doing a service change and the AHJ wants an outside disco. Does this mean I have to run a four wire system from the disco to the service panel? Doesn't this in effect make the service panel a sub-panel?

Sorry if this sounds like a DIY'ers question, it's not. I've just never done a service change where they required me to use a disco after the can.

Work Gear for Electricians and the Trades

Work Gear for Electricians and the Trades
Work Gear for Electricians and the Trades
Arc Flash Clothing, Gloves, KneePads, Tool Belts, Pouches, Tool Carriers, etc. etc....

#40767 - 08/03/04 12:22 PM Re: Outside disco
Bill Addiss Offline

Registered: 10/07/00
Posts: 4196
Loc: NY, USA
Big A,

Yes to both questions. They make Meter/Mains (Meter enclosures with a Main Breaker) that might be your easiest solution.