The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!


2017 NEC and Related
2017 NEC
Now Available!

Recent Posts
Parking lot pole light swap....
by gfretwell
Yesterday at 09:52 PM
International Wire Colour Codes
by Texas_Ranger
Yesterday at 08:24 AM
Son of Sparky
by HotLine1
10/20/16 07:43 PM
Speaking of Plugmold ...
by gfretwell
10/17/16 02:37 PM
Broken battery charger? Check for cobwebs!
by gfretwell
10/17/16 02:30 PM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 12
renosteinke 6
HotLine1 6
ghost307 5
Potseal 4
Who's Online
1 registered (geoff in UK), 213 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#213441 - 05/01/14 09:54 PM installing service lines
schenimann Offline

Registered: 02/18/08
Posts: 194
Loc: Western North Carolina
I spoke to my brother in law who is a builder in Knoxville. His electrician is responsible to install the service line to transformer with an underground service. He will trench and bring the wires into tho transformer for the poco to land. Where I live, the poco is responsible from the meter to the transformer. How many of you have to take your install to the poco transformer?

Work Gear for Electricians and the Trades

Work Gear for Electricians and the Trades
Work Gear for Electricians and the Trades
Arc Flash Clothing, Gloves, KneePads, Tool Belts, Pouches, Tool Carriers, etc. etc....

#213442 - 05/01/14 10:48 PM Re: installing service lines [Re: schenimann]
gfretwell Offline


Registered: 07/20/04
Posts: 9024
Loc: Estero,Fl,usa
Down here the customer is responsible for getting the UG lateral in but FPL will do it on a contract cheaper than most builders think they can hire an electrician to do it, so they just pay FPL.
If FPL does it the AHJ usually doesn't even inspect it. (other that what you see in the meter can)
Greg Fretwell

#213443 - 05/02/14 06:00 AM Re: installing service lines [Re: schenimann]
wire_twister Offline

Registered: 07/25/07
Posts: 265
Loc: Georgia USA
In my area the poco comes to us, we set the meter, get the inspection then the poco trenches and installs the lateral. On overhead services the poco handles everything past the weatherhead, we leave about 24 inches of wire out of the weatherhead for them to make a connection to.

Life is tough, Life is tougher when you are stupid

#213445 - 05/02/14 02:42 PM Re: installing service lines [Re: schenimann]
electure Offline


Registered: 12/24/00
Posts: 4226
Loc: Fullerton, CA USA

In SoCal the Contractor is responsible for the complete UG duct installation, and the POCO inspectors approve the installation before backfill. After backfilling, a mandrel test may be required. The electricians pull the mandrel in the inspector's presence.

The POCO supplies the cable, pull the cable, terminates it, and install the meters. (They have separate crews that for all of these tasks)

#213446 - 05/02/14 07:27 PM Re: installing service lines [Re: schenimann]
HotLine1 Offline


Registered: 04/03/02
Posts: 6791
Loc: Brick, NJ USA
NJ style in PSE&G area:
UG in an overhead area, EC installs conduit and wire to pole; 10' Sch 80 at pole, with wire to reach the OH drop.

OH in a BUD area, POCO does all to line side of meter pan. EC supplies PVC under meter pan & bell end.

OH in OH area; EC responsible to weatherhead.

PSE&G supplies meter pans (up to 320/400); drop hooks.

ECs allowed to cut & reconnect all resi service upgrades.