The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!

Featured:
   

2017 NEC and Related
2017 NEC
Now Available!

   
Recent Posts
Sprinklered equipment 26-008
by bigpapa
12/02/16 04:24 PM
On Delay Relay with Auto Reset
by Potseal
12/01/16 09:59 AM
Wow, that was close!
by jraef
11/28/16 07:06 PM
Earthquake in New Zeeland
by RODALCO
11/27/16 11:25 PM
Calling all Non-US members!! (Non-US only)
by Tjia1981
11/27/16 06:33 AM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 13
HotLine1 9
Texas_Ranger 8
sparkyinak 7
Trumpy 6
Who's Online
0 registered (), 227 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Page 1 of 2 1 2 >
Topic Options
Rate This Topic
#211434 - 10/11/13 08:27 PM Advice Needed
BigB Offline
Member

Registered: 03/31/04
Posts: 727
Loc: Tucson, AZ USA
Looking at pulling 3-4/0 aluminum XHHW conductors approx 90 feet with four long 90s (sweeps)in 2" IMC. Is this doable using 2" IMC and 2 guys? Actually we could put the end sweep together last which would reduce it to 3 90s and about 80 feet.

Top
Work Gear for Electricians and the Trades

Work Gear for Electricians and the Trades
Work Gear for Electricians and the Trades
Arc Flash Clothing, Gloves, KneePads, Tool Belts, Pouches, Tool Carriers, etc. etc....

#211435 - 10/11/13 09:35 PM Re: Advice Needed [Re: BigB]
sparkyinak Offline
Member

Registered: 07/08/07
Posts: 1295
Loc: Alaska
With no grounding conductor?

By code the conduit run should be installed first. Trying to spin a sweep on a pipe can damage the conductors. I don't have my NEC handy but I'm pretty sure you can pull the 4/0 in especially if they are compact AL conductors
_________________________
"Live Awesome!" - Kevin Carosa

Top
#211436 - 10/12/13 07:58 AM Re: Advice Needed [Re: BigB]
twh Offline
Member

Registered: 03/11/04
Posts: 898
Loc: Regina, Sask.
There are a lot of variables that you aren't sharing. Pulling up or down, feeding up or down, space to stretch cables out on the feed end, locations of the 90s, the size of the guys etc.

I think it's cheaper to have one guy stand around doing nothing than to have a crew wait for a couple hours while you find help.

Top
#211437 - 10/12/13 10:12 AM Re: Advice Needed [Re: BigB]
BigB Offline
Member

Registered: 03/31/04
Posts: 727
Loc: Tucson, AZ USA
first 90 under panel into ground then 12 feet laterally to second 90 coming up outside patio wall and into third 90 to change directions 90 degrees, then 70 feet along wall to last 90 which will sweep up into the service mast. Average guys, not weak, not Charles Atlases either.

Top
#211438 - 10/12/13 11:32 AM Re: Advice Needed [Re: BigB]
sparkyinak Offline
Member

Registered: 07/08/07
Posts: 1295
Loc: Alaska
Lube. Lotsa lube
_________________________
"Live Awesome!" - Kevin Carosa

Top
#211439 - 10/12/13 12:22 PM Re: Advice Needed [Re: BigB]
twh Offline
Member

Registered: 03/11/04
Posts: 898
Loc: Regina, Sask.
3 guys.

2 guys on the feed end to start. One guy pulls slack in the cable and the other pushes and lubes. "Pulling wire" is misleading. Half the job is pushing the wire.

After halfway, move one guy to the other end to help pull. Pulling up makes it hard to have more than two guys on the rope, anyway.

Don't forget lotsa rags to go with the lotsa lube.

If you try with two guys, you might need to pull one 90 off and tie the rope to something to give you more leverage - like a 2x4 and a fulcrum or maybe even a truck. It might go okay, but it might suck for many hours.

It would be nice to feed from the end closest to the most 90s. I think lubed cable slides around a 90 easier than a dry rope.

Top
#211440 - 10/12/13 06:00 PM Re: Advice Needed [Re: BigB]
gfretwell Offline

Member

Registered: 07/20/04
Posts: 9045
Loc: Estero,Fl,usa
You could put a conduit body somewhere along the way to break up the pull. Maybe an LB at the "change of direction" after you get up out of the ground.
Think about where you get the best place to work.
_________________________
Greg Fretwell

Top
#211442 - 10/13/13 12:07 PM Re: Advice Needed [Re: BigB]
BigB Offline
Member

Registered: 03/31/04
Posts: 727
Loc: Tucson, AZ USA
No conduit bodies before the meter are allowed by the POCO. I decided to go with 2.5" pipe.

Top
#211443 - 10/13/13 12:33 PM Re: Advice Needed [Re: BigB]
sparkyinak Offline
Member

Registered: 07/08/07
Posts: 1295
Loc: Alaska
That's gonna be a jump on material price. Anything over 2" in size, thei cost goes up expotentially

Is there a way to use an ordinary come-along or winch of some type?
You can use a choker on the rope a what is called a French prusik. It works on the same principle as a choker but you use a small peice of rope. It's easier on the rope than a choker can be

The link is how to use a prusik. It's a variant of the one I use but it works and simple to use

http://m.youtube.com/watch?v=u0YxU5C_KrQ

With some type of winch or even with block and tackle one person can feed while one person pulls even with the biggest and longest pulls


Edited by sparkyinak (10/13/13 12:35 PM)
_________________________
"Live Awesome!" - Kevin Carosa

Top
#211444 - 10/13/13 02:50 PM Re: Advice Needed [Re: sparkyinak]
BigB Offline
Member

Registered: 03/31/04
Posts: 727
Loc: Tucson, AZ USA
Originally Posted By: sparkyinak
That's gonna be a jump on material price. Anything over 2" in size, thei cost goes up expotentially

Is there a way to use an ordinary come-along or winch of some type?
You can use a choker on the rope a what is called a French prusik. It works on the same principle as a choker but you use a small peice of rope. It's easier on the rope than a choker can be

The link is how to use a prusik. It's a variant of the one I use but it works and simple to use

http://m.youtube.com/watch?v=u0YxU5C_KrQ

With some type of winch or even with block and tackle one person can feed while one person pulls even with the biggest and longest pulls


Yes I have a come-along, a high lift jack and a boat winch and I have considered using one of them.

Thanks for the link