Locked rotor, no burnout
by andey
Today at 04:48 AM
Temporarily feeding a panel...
by Potseal
Yesterday at 11:05 PM
Massive power outage South Australia
by Meadow
Yesterday at 06:46 AM
short circuit??
by Meadow
Yesterday at 06:43 AM
Norwegian power?
by Meadow
Yesterday at 06:36 AM
New in the Gallery:
12.5A through 0.75mm² flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
HotLine1 14
sparky 10
sparky66wv 8
gfretwell 8
Potseal 7
Who's Online
1 registered (gfretwell), 282 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#201849 - 06/28/11 09:16 AM Overhead Three Phase 13.8 & 4160 Delta
Yoopersup Offline
Member

Registered: 03/04/03
Posts: 826
Loc: Michigan
Overhead 13.8 & 4160 Delta no neutral present.
Running to remote building . Owners Not Utilitys.
When you come down pole to Step down Transformer where & how do you ground?
If ungrounded delta how does it trip ocp , located remotely??
Remember its Owners , Not Utlity so there Feeders!
Yoopersup

Top
2014 / 2011 NEC & Related Books and Study Guides
#201857 - 06/28/11 05:26 PM Re: Overhead Three Phase 13.8 & 4160 Delta [Re: Yoopersup]
renosteinke Offline
Cat Servant
Member

Registered: 01/22/05
Posts: 5300
Loc: Blue Collar Country
You ground / bond to the case of the transformer.

The OCPD trips only after the SECOND line faults to ground. That's why phase monitors are required.

Non-NEC compliant solution: Slap the foolishness out of this customer- there's no reason to preserve an ungrounded delta.

Top
#201860 - 06/28/11 05:51 PM Re: Overhead Three Phase 13.8 & 4160 Delta [Re: Yoopersup]
Yoopersup Offline
Member

Registered: 03/04/03
Posts: 826
Loc: Michigan
Design By Electrical Engineer!
Phase monitors on a overhead line? 4160.
Or 13800 volts?? Please give details .

Top
#201871 - 06/28/11 09:49 PM Re: Overhead Three Phase 13.8 & 4160 Delta [Re: Yoopersup]
gfretwell Online   content

Member

Registered: 07/20/04
Posts: 9012
Loc: Estero,Fl,usa
The medium voltage lines around my area seem to have some kind of impedance grounding going on. You see a funny looking insulator device connected to ground every so often along the line. I suspect this is just a path for lightning,
_________________________
Greg Fretwell

Top
#201874 - 06/28/11 11:35 PM Re: Overhead Three Phase 13.8 & 4160 Delta [Re: Yoopersup]
frenchelectrican Offline

Member

Registered: 02/06/03
Posts: 938
Loc: Wi/ Paris France { France for ...
Originally Posted By: Yoopersup
Design By Electrical Engineer!
Phase monitors on a overhead line? 4160.
Or 13800 volts?? Please give details .


Ya sérieux ??

What kind of ground fault detector you have or will set up most common in MV/HV class will have impleaded or resteror grounded or netural set up depending on the supply format is.

And you will need phase monitor to detect the ground fault on them and some case you may need automatique recloser { this part I am not too crazy but it do work very well }

Merci,
Marc
_________________________
Pas de problme,il marche n'est-ce pas?"(No problem, it works doesn't it?)


Top