Had some fun today. We replaced lightning arrestors, and clearly cut-outs, installed bird wire and raptor guards at a 3 phase transformer bank (21KV Pri/480V ungrounded delta secondary)

The cutout in the photo was still functioning, although it had suffered a lighting strike during our last storms.. The #6 cu bonding wire was blown to bitsbetween this cutout and the next





Top
Tools for Electricians:
#185916 - 04/04/09 01:23 PM Re: Lightning Strike [Re: Lostazhell]
packrat56 Offline
Member
Registered: 03/03/08
Posts: 76
Loc: MT, U.S.
Wow, well that's lightning for you.
_________________________
I have a sense of adventure, I just keep it leashed with common sense.
Top

Member Spotlight
Member Since: 11/17/00
Posts: 2232
New in the Gallery:
SE cable question
Featured:

2017 NEC and Related
2017 NEC
Now Available!

Shout Box


Who's Online
0 registered (), 52 Guests and 8 Spiders online.
Key: Admin, Global Mod, Mod
 
New in the Gallery:
SE cable question
 
Top Posters (30 Days)
Admin 47
HotLine1 43
gfretwell 19
Ruben Rocha 12
Trumpy 9
 
Newest Members
Freecrowder, clee512, Jdscott2005, FAIZAN, Regitest2

ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals