The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!

Featured:
   

2017 NEC and Related
2017 NEC
Now Available!

   
Recent Posts
Sprinklered equipment 26-008
by bigpapa
12/02/16 04:24 PM
On Delay Relay with Auto Reset
by Potseal
12/01/16 09:59 AM
Wow, that was close!
by jraef
11/28/16 07:06 PM
Earthquake in New Zeeland
by RODALCO
11/27/16 11:25 PM
Calling all Non-US members!! (Non-US only)
by Tjia1981
11/27/16 06:33 AM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 15
HotLine1 10
Trumpy 8
Texas_Ranger 8
sparkyinak 7
Who's Online
1 registered (sparkyinak), 237 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Page 1 of 3 1 2 3 >
Topic Options
Rate This Topic
#184816 - 02/22/09 07:04 PM t&m vs. flat rate for service?
jdot77 Offline
Member

Registered: 03/06/07
Posts: 16
Loc: Riverview, Fl
hey guys im new to the forum. I just started a small elec buss. I was wanting any feedback on how you guys are charging cutomers. any thoughts on T&M vs. Upfront pricing would be greatly appreciated!
_________________________
jason

Top
Business, Office, Estimating, Legal:
#184820 - 02/22/09 07:55 PM Re: t&m vs. flat rate for service? [Re: jdot77]
dougwells Offline

Member

Registered: 05/03/03
Posts: 1228
Loc: kamloops BC Canada
I am a Flat rate company Upfront pricing is listed in all my advertising. Now saying that I am my own worst enemy when quoting from a price book. i start to second guess my final price
why am I more concerned about the customers ability to pay than my own operating expenses.. I think I need one of those Charlie Greer seminars smile

Top
#184823 - 02/22/09 08:43 PM Re: t&m vs. flat rate for service? [Re: dougwells]
renosteinke Offline
Cat Servant
Member

Registered: 01/22/05
Posts: 5305
Loc: Blue Collar Country
T&M requires a great deal of trust between the customer and the contractor. It can only work after a long standing relationship has developed.

As for "flat rate," we ALL like to know ahead of time what we can expect to spend. Would you roder at a restaurant, without knowing the cost?

Top
#184829 - 02/23/09 07:49 AM Re: t&m vs. flat rate for service? [Re: renosteinke]
jdot77 Offline
Member

Registered: 03/06/07
Posts: 16
Loc: Riverview, Fl
Now with a flat rate pricing, do you go to each customers house with a estimate, or do you give estimate over phone without seeing project? running around not getting jobs could be and issue, unless you could give price over phone. I like the idea of flat rate, but seems like you would be losing alot of time on the road as well.
_________________________
jason

Top
#184832 - 02/23/09 11:11 AM Re: t&m vs. flat rate for service? [Re: jdot77]
dougwells Offline

Member

Registered: 05/03/03
Posts: 1228
Loc: kamloops BC Canada
Generally flat rate has a dispatch charge attached to it. It is not a good Idea to quote task prices over the phone you need to see the job.

Top
#184846 - 02/23/09 06:36 PM Re: t&m vs. flat rate for service? [Re: dougwells]
jdot77 Offline
Member

Registered: 03/06/07
Posts: 16
Loc: Riverview, Fl
how do you combat the contractors that are giving free estimates. With the dispatch fee you may not get to see alot of jobs available. Customers that are looking for an electrician will tend to be looking for free estimates.
Which is not hard to find! Basically it sounds like the dispatch fee is a charged estimate.

Thanks for all the input on this topic
_________________________
jason

Top
#184856 - 02/23/09 08:19 PM Re: t&m vs. flat rate for service? [Re: jdot77]
dougwells Offline

Member

Registered: 05/03/03
Posts: 1228
Loc: kamloops BC Canada
Thanks to Aline for posting this link at another forum.
It helps to determine how to apply a dispatch fee to go look at a site.

http://contractingbusiness.com/ar/cb_imp_13003/

Top
#184858 - 02/23/09 10:03 PM Re: t&m vs. flat rate for service? [Re: dougwells]
jdot77 Offline
Member

Registered: 03/06/07
Posts: 16
Loc: Riverview, Fl
hey thanks, thats was very informatable.
_________________________
jason

Top
#184861 - 02/24/09 07:51 AM Re: t&m vs. flat rate for service? [Re: jdot77]
leland Offline
Member

Registered: 08/20/07
Posts: 856
Loc: Lowell area, Ma. USA
Thanx Doug. That was great.
I have long been Leary of a flat rate. This article (as opposed to others)Has really got me thinking.

I don't think I ever had the full grasp of it before.

I have walked away after a T&M job shaking my head at all the money I didn't make.

Top
#184870 - 02/24/09 02:11 PM Re: t&m vs. flat rate for service? [Re: leland]
macmikeman Offline
Member

Registered: 07/16/02
Posts: 718
Loc: Honolulu, Hawaii
Originally Posted By: leland

I have walked away after a T&M job shaking my head at all the money I didn't make.


Leland, if it is any consolation, I have walked away after some flat rate calls shaking my head at all the money I didn't make either. It doesn't always work out, but by far it does based on percentages of times it does. Trick is do not "flat rate" at only what you think it will take to do the job and make a profit at it. Figure the worst case scenerio into it and flat rate based on that. Then you start making money at flat rate cause it will even out the ones you don't figure enough time into to get it done right and to super service. One thing about that Charlie Greer article , If you drop your trip charge and then bury it back into the primary task, isn't that the same thing as "free estimate" when in fact you end up charging for that free estimate in price of the job....