The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!

Featured:
   

2017 NEC and Related
2017 NEC
Now Available!

   
Recent Posts
Temporarily feeding a panel...
by renosteinke
09/29/16 05:10 PM
Locked rotor, no burnout
by jraef
09/29/16 01:18 PM
Massive power outage South Australia
by Meadow
09/29/16 06:46 AM
short circuit??
by Meadow
09/29/16 06:43 AM
Norwegian power?
by Meadow
09/29/16 06:36 AM
New in the Gallery:
12.5A through 0.75mm˛ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
HotLine1 13
sparky 10
sparky66wv 8
gfretwell 8
Potseal 6
Who's Online
1 registered (mbhydro), 296 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#180521 - 08/28/08 06:25 PM Another question for inspectors
wire_twister Offline
Member

Registered: 07/25/07
Posts: 265
Loc: Georgia USA
What do you guys think about sight wells in lieu of leaving a trench open. How many would you require, and where would they be placed?
_________________________
Jimmy

Life is tough, Life is tougher when you are stupid

Top
Work Gear for Electricians and the Trades

Work Gear for Electricians and the Trades
Work Gear for Electricians and the Trades
Arc Flash Clothing, Gloves, KneePads, Tool Belts, Pouches, Tool Carriers, etc. etc....

#180523 - 08/28/08 06:38 PM Re: Another question for inspectors [Re: wire_twister]
sparkyinak Offline
Member

Registered: 07/08/07
Posts: 1286
Loc: Alaska
If it is not practical for an open site inspection I have no problem on sight wells. This is a case by case basis. If there critcal issues with like bedding or compacting then sight well may not be the way to go. Same applies with the number of wells.

As far as where they would shound be placed, I would recommend above the buried conduit(s). If they were on the side or underneath the conduit, it would sort of be a mute point. \:\) All kidding aside, It is all a case by case basis. I think there are too many varibles to figure on to give a rule of thumb answer.
_________________________
"Live Awesome!" - Kevin Carosa

Top
#180524 - 08/28/08 06:52 PM Re: Another question for inspectors [Re: sparkyinak]
wire_twister Offline
Member

Registered: 07/25/07
Posts: 265
Loc: Georgia USA
All these out of work comedians, and the sparkys are trying to move in!!
_________________________
Jimmy

Life is tough, Life is tougher when you are stupid

Top
#180525 - 08/28/08 07:35 PM Re: Another question for inspectors [Re: wire_twister]
sparkyinak Offline
Member

Registered: 07/08/07
Posts: 1286
Loc: Alaska
Must keep all options open
_________________________
"Live Awesome!" - Kevin Carosa

Top
#180531 - 08/29/08 03:34 AM Re: Another question for inspectors [Re: sparkyinak]
SteveFehr Offline
Member

Registered: 03/19/05
Posts: 1192
Loc: Chesapeake, VA
They should be placed at ground level. We've had difficulty elevating them in the past, and the AHJs don't like to have to climb ladders.

Top
#180540 - 08/29/08 08:48 AM Re: Another question for inspectors [Re: SteveFehr]
HotLine1 Offline

Member

Registered: 04/03/02
Posts: 6785
Loc: Brick, NJ USA
As Alaska said, it's a case-by-case decision for me. Sometimes access has to be maintained for equipment, so a partial backfill is necessary, as long as I can see both sides, OK.

Going to a site and seeing the pole bases in place, and the parking lot sub-base down, now that causes an issue, start digging.

As to site wells, short lengths of PVC sitting on top of the conduit run and above grade may be acceptable, but on a case-by-case decision.

In any case, the EC should talk to the AHJ BEFORE hand to determine what is acceptable. Communications are cheaper then digging twice!
_________________________
John

Top
#180605 - 09/01/08 06:40 AM Re: Another question for inspectors [Re: HotLine1]
harold endean Offline
Member

Registered: 02/16/02
Posts: 2248
Loc: Boonton, NJ
John is correct when he says to call the AHJ before starting any work. It is much easier than digging twice. I have people tell me all the time, "I took pictures!" The problem with that is after awhile, all the trenches look the same! I don't even look at pictures anymore. I would rather they use the sight pipe and back fill area that are critical for moving cars and machinery around the sight. Places like parking lots and condos where the trench is in the road, it would be to dangerous to leave the road open.

Top
#180611 - 09/01/08 01:27 PM Re: Another question for inspectors [Re: harold endean]
Tom Offline
Member

Registered: 01/01/01
Posts: 1069
Loc: Shinnston, WV USA
I get along with sight wells, mainly when the trench is in a mobile home park or residential area. You still need to call me ahead of time though. No call, no sight well = shovel.
_________________________
Few things are harder to put up with than the annoyance of a good example.

Top



ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals