#175817 - 03/11/08 07:30 PM 'Temporary' Transformer Hookup
Admin Offline

Administrator
Member
Registered: 10/07/00
Posts: 3417
Loc: NY, USA
Quote:
Hows this for temporary?

This Trani blew a few yrs back. Now they won't give us a shut down to replace it.

- Leland



Top
Tools for Electricians:
#175897 - 03/14/08 12:53 AM Re: 'Temporary' Transformer Hookup [Re: Admin]
Trumpy Offline


Member
Registered: 07/05/02
Posts: 8211
Loc: SI,New Zealand
OK then,
Now, who is responsible for this mess?
You have an open panel with terminals exposed.

So, "they" won't let you shut this down?
What does this transformer supply?
Even more to the point, who are "they"?
There is absolutely no reason why something like this cannot be shut down, anyone who says to the contrary, is dreaming.

Just my opinion.
_________________________
Let's face it, these days if you're not young, you're old - Red Green grin
Top
#175910 - 03/14/08 11:00 AM Re: 'Temporary' Transformer Hookup [Re: Admin]
LarryC Offline
Member
Registered: 07/05/04
Posts: 780
Loc: Winchester, NH, US
Is that a breaker panel that reaches all the way down to the floor? It looks like the bottom breakers are only 12" from the floor.

Larry C
Top
#175939 - 03/15/08 09:35 AM Re: 'Temporary' Transformer Hookup [Re: LarryC]
sparkyinak Offline
Member
Registered: 07/08/07
Posts: 1307
Loc: Alaska
Customers are willing to pay a high price to be cheap. Years ago, a couple of co-workers went to investigate a transformer at a foundry. It was a oil filled can like the POCO's use on poles. The lid blew off and half the oil boiled off and the customer wanted to know if they can keep running it that way. I do not believe they were running 24/7 operations at the time. They just did not want give up the money. Even when money is tight, you think it was a no brainer.
_________________________
"Live Awesome!" - Kevin Carosa
Top
#175940 - 03/15/08 09:36 AM Re: 'Temporary' Transformer Hookup [Re: LarryC]
leland Offline
Member
Registered: 08/20/07
Posts: 853
Loc: Lowell area, Ma. USA
Mike, A world renouned college, Known for its Engineering wonders of the world. (Big dome )

This is a distribution panel for 120/240 lab panels a and class rooms. RE; shut down, your right.
The bottom line is they don't want to pay OT!!.

Larry, we have the 12" at the bottom.

This is a 225 KVA 480-240. My surprise, 2002!!!! 6 YEARS!!!
I guess their priority is the students.
Top
#175941 - 03/15/08 09:38 AM Re: 'Temporary' Transformer Hookup [Re: leland]
sparkyinak Offline
Member
Registered: 07/08/07
Posts: 1307
Loc: Alaska
I work for the government. 6 years is still considered temporary. smile
_________________________
"Live Awesome!" - Kevin Carosa
Top
#175942 - 03/15/08 09:56 AM Re: 'Temporary' Transformer Hookup [Re: sparkyinak]
leland Offline
Member
Registered: 08/20/07
Posts: 853
Loc: Lowell area, Ma. USA
Originally Posted By sparkyinak
I work for the government. 6 years is still considered temporary. smile


You aint kidding!! Temporarily permanent!
Top
#175981 - 03/17/08 01:18 AM Re: 'Temporary' Transformer Hookup [Re: leland]
Texas_Ranger Offline
Member
Registered: 12/17/01
Posts: 2391
Loc: Vienna, Austria
In Austria they say temporary solutions usually last longer than permanent ones... in 1892 the city built a temporary subway station (temporary becaus it was close to a bridge scheduled for a major redesign and they planned to build the permanent station after the bridge work was completed). The temporary station lasted until about 1960... the permanent station built afterwards was demolished again in 1978. So that makes 68 years for the temp solution and 28 for the permanent... nice, huh?
Top
#176082 - 03/19/08 06:58 PM Re: 'Temporary' Transformer Hookup [Re: leland]
Elviscat Offline
Member
Registered: 08/13/05
Posts: 214
Loc: Seattle Washington USA
Considering the U I think this is, it makes it all the more funny, not exactly an engineering or technological masterpiece.

-Will
Top
#176095 - 03/20/08 08:58 AM Re: 'Temporary' Transformer Hookup [Re: leland]
SteveFehr Offline
Member
Registered: 03/19/05
Posts: 1195
Loc: Chesapeake, VA
Originally Posted By leland
Mike, A world renouned college, Known for its Engineering wonders of the world. (Big dome )

This is a distribution panel for 120/240 lab panels a and class rooms. RE; shut down, your right.
The bottom line is they don't want to pay OT!!.

Larry, we have the 12" at the bottom.

This is a 225 KVA 480-240. My surprise, 2002!!!! 6 YEARS!!!
I guess their priority is the students.
I've see the same situation more times than I care to count... our problem isn't cost though (well, not always) but unwillingness to schedule downtime. Hey, power's still flowing so it might be OK, right??
Top
Page 1 of 2 1 2 >

Member Spotlight
Member Since: 08/22/05
Posts: 44
New in the Gallery:
SE cable question
Featured:

2017 NEC and Related
2017 NEC
Now Available!

Shout Box


Who's Online
0 registered (), 30 Guests and 8 Spiders online.
Key: Admin, Global Mod, Mod
 
New in the Gallery:
SE cable question
 
Top Posters (30 Days)
Admin 47
HotLine1 43
gfretwell 19
Ruben Rocha 12
Trumpy 9
 
Newest Members
Scotto, Freecrowder, clee512, Jdscott2005, FAIZAN

ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals