The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Topic Options
Rate This Topic
#170822 - 11/12/07 05:30 PM ditch depth under "pavers"??
sparkync Offline
Member
Registered: 10/17/02
Posts: 811
Loc: NC
I know the depth under cement is normally 4 " with RNC, but just wondering if the depth could be the same with paving stones? The job I'm on is having pavers put down around their pool ( proffesionally ) with gravel etc. and the installer said you would have to drill the pavers out. As far as I know the code don't specify this as an option, but what do you think an inspector might say about this?? I'll probably go the 12" rule for circuits that are GFI protected and rated 20 amps or less, but in this case it would be NICE to have it the same as concrete. I hate to bug the inspectors any more than I have to. I've called on them quiet a bit lately. Thanks, Steve
Top
2017 / 2014 NEC & Related Books and Study Guides
#170826 - 11/12/07 06:39 PM Re: ditch depth under "pavers"?? [Re: sparkync]
gfretwell Offline


Member
Registered: 07/20/04
Posts: 9066
Loc: Estero,Fl,usa
300.5 uses the words "concrete" and "slab". That can't be confused with pavers. I won't say your AHJ won't go along but I am not sure how.
RNC is only 6" anyway so he might consider 2" of paver as being part of the 6" cover. Keep it 5' away from the water if at all possible.
_________________________
Greg Fretwell
Top
#170831 - 11/13/07 07:18 AM Re: ditch depth under "pavers"?? [Re: gfretwell]
Zapped Offline
Member
Registered: 10/01/02
Posts: 481
Loc: Huntington Beach, CA, USA
I agree with Greg on 300.5, as concrete is more of a continuious material, and more "permenant" in a sense.

However, I have SEEN RNC laid to about 6" below paver bottoms and also have seen it pass inspection. As far as "drilling out" the pavers, I'd have to question the logic in this, if I'm getting what you mean.

If acheiving a 12" depth is an issue, you might have to bite the bullet and inquire with the AHJ as to how he inturprets 300.5. A screw up here could cause a re-do, and nobody wants to work for free!

Good Luck!
Top
#170834 - 11/13/07 08:26 AM Re: ditch depth under "pavers"?? [Re: Zapped]
gfretwell Offline


Member
Registered: 07/20/04
Posts: 9066
Loc: Estero,Fl,usa
Using RNC I am not sure when it ever needs to be more than 6" down if you aren't going under a road, runway or parking lot.
Look at 680.10 for a more specific answer. You still see 6" and I could see how an AHJ might measure from the top of the paver.
_________________________
Greg Fretwell
Top
#170853 - 11/13/07 05:14 PM Re: ditch depth under "pavers"?? [Re: gfretwell]
George Little Offline
Member
Registered: 01/18/04
Posts: 1492
Loc: Michigan USA
Greg- You guys are talking about RNC not RMC Double check your comments. (I think)
_________________________
George Little
Top
#170856 - 11/13/07 05:35 PM Re: ditch depth under "pavers"?? [Re: George Little]
gfretwell Offline


Member
Registered: 07/20/04
Posts: 9066
Loc: Estero,Fl,usa
I typed it several times and still never realized we weren't talking about "rigid".
Sorry for the confusion.
I guess that is why I used to always say RNMC for the plastic.
_________________________
Greg Fretwell
Top
#170860 - 11/13/07 05:55 PM Re: ditch depth under "pavers"?? [Re: gfretwell]
George Little Offline
Member
Registered: 01/18/04
Posts: 1492
Loc: Michigan USA
I'll let it slide this time Greg but only this time frown
_________________________
George Little
Top
#170874 - 11/13/07 07:01 PM Re: ditch depth under "pavers"?? [Re: George Little]
renosteinke Offline
Cat Servant
Member
Registered: 01/22/05
Posts: 5305
Loc: Blue Collar Country
I really hate to sound like a broken record .... but does not Section 90 of the NEC plainly state "this is not a design manual?"

So, how deep should the pipe be buried? Well, as deep as it needs to be when it exits from the protection of the slab, would be a good start. Or, do you plan on changing the trench depth every time you have a change of the surface material? Lots of luck sanding the angled parts.

Or, consider this: what's a likely cause for the pipe being damaged? Besides the gardener using his shovel to look for irrigation lines ... how about frost heave? I don't care how well the pavers are laid .... give them a few frost cycles, and they'll be all over the place. Maybe the angled pavers will now even act like scissors on your pipe.

Whatever depth you decide upon, make it an honest depth. That is, to the top of the pipe, after it's properly bedded in sand - and NOT the rough depth of the trench! This means a 6" burial depth starts off with a 12" ditch.
Top

Featured:

2017 NEC and Related
2017 NEC
Now Available!

Shout Box

Recent Posts
Looking for older post
by sparkyinak
Today at 12:27 AM
License exam
by TRUE POWER
Yesterday at 11:33 PM
Members: Non-Members: Did you know?
by Admin
Yesterday at 02:34 PM
Safety at heights?
by HotLine1
01/21/17 08:51 PM
International Wire Colour Codes
by Texas_Ranger
01/21/17 03:29 PM

Who's Online
0 registered (), 66 Guests and 9 Spiders online.
Key: Admin, Global Mod, Mod
New in the Gallery:
Desk-mounted "power-board"
Top Posters
gfretwell 9066
Trumpy 8560
pauluk 7693
HotLine1 6833
sparky 5545
Member Spotlight
Tom
Tom
Member Since: 01/01/01
Posts: 1069

ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals