The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Register Now!

Register Now!

We want your input!


2017 NEC and Related
2017 NEC
Now Available!

Recent Posts
Parking lot pole light swap....
by gfretwell
Yesterday at 09:52 PM
International Wire Colour Codes
by Texas_Ranger
Yesterday at 08:24 AM
Son of Sparky
by HotLine1
10/20/16 07:43 PM
Speaking of Plugmold ...
by gfretwell
10/17/16 02:37 PM
Broken battery charger? Check for cobwebs!
by gfretwell
10/17/16 02:30 PM
New in the Gallery:
12.5A through 0.75mm▓ flex (just out of curiosity)
Shout Box

Top Posters (30 Days)
gfretwell 12
renosteinke 6
HotLine1 6
ghost307 5
Potseal 4
Who's Online
1 registered (geoff in UK), 213 Guests and 4 Spiders online.
Key: Admin, Global Mod, Mod
Topic Options
Rate This Topic
#166410 - 07/19/07 10:55 PM What to do?
Trumpy Offline


Registered: 07/05/02
Posts: 8532
Loc: SI,New Zealand
At a local factory here, I recently installed 3 x 630mm2 Al conductors in PVC conduit and laid it nicely in fine sand (called crusher dust here), laid a heavy duty warning strip over the top of it at half trench depth, all well and good I thought when it was back-filled.
I now find out this morning that the guy excavating a trench for the storm-water drains, dredged up my warning strip and conduit in one fowl swoop, even when told by one of the builders on site there were cables buried in the area where he was digging.
Luckily, these cables (singles actually) haven't been livened yet, as they aren't required, as the 2nd stage of the factory hasn't taken place yet and I am still waiting on the switchboard to be fabricated.
But, I was supposed to be going on holiday today for 3 weeks, something tells me that won't be happening.
I got there this afternoon and all I saw was a big orange curve sticking out of the ground and stripped aluminium cables sticking out of the conduit.
Believe me guys, I was nearly in tears, I put a LOT of work into that pull and to see it like that was devastating.
What do I do from here though?, do I get the lot dug up and start again?.
The conduit (glued PVC) has obviously come apart further down the trench.
With the size of conductor involved, I don't feel comfortable with jointing it either, considering it will be carrying something like 400-700A per core.
What would you do?.
Let's face it, these days if you're not young, you're old - Red Green grin

Test Equipment:

Large Selection of Test Equipment For Electrical, HVAC, Test & Measurement
Large Selection of Test Equipment For Electrical, HVAC, Test & Measurement

#166412 - 07/20/07 12:19 AM Re: What to do? [Re: Trumpy]
Kenbo Offline

Registered: 04/07/06
Posts: 234
Loc: Scotland
Go on holiday (the wife wont forgive you if you dont)
Sub contract someone to replace the cable and give the bill to the digger driver!!!!
der Gro├čvater

#166427 - 07/20/07 07:06 AM Re: What to do? [Re: Kenbo]
renosteinke Offline
Cat Servant

Registered: 01/22/05
Posts: 5305
Loc: Blue Collar Country
Kenbo has it .... replace and backcharge. When the law frowns on hitting them in the nose, hit them in the pocketbook!

#166429 - 07/20/07 08:03 AM Re: What to do? [Re: renosteinke]
EV607797 Offline

Registered: 10/25/06
Posts: 756
Loc: Fredericksburg, VA, USA
That's an eerily similar story to a situation that we encountered a few years ago. We were contracted to bury a telephone cable at a new high school that was under construction. The Friday before we started the job (the following Monday), I stopped by to survey the conditions. We only had one potential crossing of existing PVC (4 X 2") containing #4 cables for tennis court lighting. They were newly-installed and about 5' deep in the ground. I mean they were so deep that I got nervous getting close to the edge of their open trench!

Knowing how deep they were, I told my installers to just keep it shallow when crossing that spot. Monday came along, they started trenching at a pretty good pace. When they got to the conduit crossing, the trench had already been backfilled and compacted. They planned to use the trencher just to break the surface of the soil and then dig that part by hand. As soon as the trencher's blade hit the ground, it pulled up all four conduits and broke them. They were now less than one inch in the ground!

The electrical contractor demanded that we pay them for the damage. We refused and were promptly sued. Our argument was that these conduits were not buried at the proper depth per NEC and that even a simple sign or fence post could have easily caused the same damage.

It turns out that we had major heavy rains over the weekend. The general contractor brought in an emergency grading crew on Sunday to deflect the grade & improve runoff. They forgot to tell anyone that this had occurred.

When we went to court, we countersued the GC citing that it was their responsibility to inform the EC that they would need to move their conduits. They had also neglected to tell us about this, even though their superintendent was right there when be damaged the conduits. The EC ended up winning against us, but we ended up winning our countersuit against the general contractor. The judge simply told them to work it out between themselves.

"But the guy at Home Depot said it would work."

#166435 - 07/20/07 02:48 PM Re: What to do? [Re: EV607797]

Registered: 12/08/05
Posts: 862
Loc: Titirangi, Akld, New Zealand
Mike, i know that feeling. Here in Auckland it happens all the time by el cheapo subbies who don't get cable runs marked out.

Firstly: I hope you got paid for that part of the job ?

Secondly: Take yourself and your misses out for a holiday.

Third: When back from your break, quote for repair or new cables. costs to be paid for by guy who damaged the cables.

Good luck ! \:D and enjoy your deserved break.

The product of rotation, excitation and flux produces electricty.

#168211 - 08/29/07 04:58 AM Re: What to do? [Re: RODALCO]
kiwi Offline

Registered: 12/04/04
Posts: 347
Loc: christchurch new zealand
Surely the diggers insurance will pay for the whole cable to be re-installed or joined.

Go on holiday Trumpy.


ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals