#124107 - 08/09/06 06:11 PM How Many Before it's Considered Conduit?
Webmaster Offline

Administrator
Member

Registered: 10/07/00
Posts: 3142
Loc: NY, USA
 Quote:
How Many Before it's Considered Conduit?

- aasu (Wes)

Top
Tools for Electricians:
#124108 - 08/10/06 04:05 PM Re: How Many Before it's Considered Conduit?
HotLine1 Offline

Member

Registered: 04/03/02
Posts: 6804
Loc: Brick, NJ USA
OK, 2 points for the marking on the cover. Then, 102 minus points for the rest.

More quality workmanship. Support/straps?? I won't even say 'box-fill'

John
_________________________
John

Top
#124109 - 08/12/06 06:01 AM Re: How Many Before it's Considered Conduit?
electure Offline

Member

Registered: 12/24/00
Posts: 4226
Loc: Fullerton, CA USA
It looks like part of this was the installer's plan from the beginning. The "main box" in this thing is an extension.
The front extension has been added later.

Take off another 6 points for the open KO in the bottom of the real box.




[This message has been edited by electure (edited 08-12-2006).]

Top
#124110 - 08/15/06 10:08 AM Re: How Many Before it's Considered Conduit?
RSmike Offline
Member

Registered: 11/27/02
Posts: 130
Loc: Holland, MI USA
Is this a remodel. I have yet to see a remodel job where flex doesn't look terrible when done. Unless you are starting new, forget it. If you want nice you're gonna run the solid pipe stuff....what's that called? Oh yeah I remember, EMT/RNC/IMC conduit...RNC if you mean business.....

Good, Fast, or Cheap : Pick two and only two. How do you compete with someone that runs around installing this flexible junk vs. installing real conduit.

Unless the box fill has be violated I don't have an issue. It doesn't look nice but I can let that slide.

Unfortunately the workmanship part is the first thing to go when trying to meet budget. It's the one thing that is fuzzy as far as code goes. How many guys still paint the plywood board behind the load panel gray? I haven't seen it done in a LONG time. It looked nice but really it served no useful purpose.

Sorry just venting a little.

RSlater,
RSmike

Top
#124111 - 08/16/06 06:10 PM Re: How Many Before it's Considered Conduit?
HotLine1 Offline

Member

Registered: 04/03/02
Posts: 6804
Loc: Brick, NJ USA
Almost a week later, & I remembered...are the connectors NOT for EMT???

Electure:
Good call, didn't notice that.

John
_________________________
John

Top
#124112 - 08/19/06 10:03 AM Re: How Many Before it's Considered Conduit?
Tesla Offline
Member

Registered: 06/16/04
Posts: 1280
Loc: Sacramento, CA
This box would appear to have a history.

A trooper placed a 4-11 box with twin 1" KOs at all four sides with the intention of running a 1" EMT feed.

Subsequently that scheme was changed to twin 3/4" EMT ... line and load. A 4-11 TKO extension ring was used providing appropriate knockout options: MC & EMT.

1" KO seal wasn't at hand... overlooked in the crush of events.

Box fill may be okay as many wires probably route in and out without make-up.

Digging past these conductors is too much when stabbing in yet more lighting whips so a second 4-11 TKO ring was used.

Lighting whips in MC running under six feet are permitted to omit strapping rules if in an accessable ceiling space.

2002 NEC 330.30 (B)(2)
_________________________
Tesla

Top
#124113 - 08/27/06 03:42 AM Re: How Many Before it's Considered Conduit?
Surfinsparky Offline
Member

Registered: 07/29/05
Posts: 77
Loc: merritt island fl usa
Say what ya want.But that is terrible.How do say not on my watch.Just me I try to never use the ko's in an extension ring.

Top
#124114 - 08/27/06 03:22 PM Re: How Many Before it's Considered Conduit?
renosteinke Offline
Cat Servant
Member

Registered: 01/22/05
Posts: 5305
Loc: Blue Collar Country
A note about the connectors...

There actually exists an MC sonnector that looks, for all the world, like an ENT set-screw connector. Not until you remove the MC can you see the light metal piece within, thaat grips the MC.

Top
#124115 - 08/29/06 05:53 PM Re: How Many Before it's Considered Conduit?
HotLine1 Offline

Member

Registered: 04/03/02
Posts: 6804
Loc: Brick, NJ USA
Reno:
Thank you re: the connectors, sure look like EMT to my old eyes.

As a side comment, if these are lighting whips, there sure must be a lot of light fixtures around this box.

John
_________________________
John

Top
#124116 - 09/21/06 06:19 PM Re: How Many Before it's Considered Conduit?
electrictim510 Offline
Member

Registered: 09/20/06
Posts: 23
Loc: Richmond, CA, 94804
I feel sorry for the person who troubleshoots the circuits in the original circuits in the box mounted to the wall.

Top