#120277 - 04/04/05 03:52 PM Working Space- Services- 220.26(A)3
Webmaster Offline

Administrator
Member

Registered: 10/07/00
Posts: 3142
Loc: NY, USA
 Quote:
The NEC defines the heigth of the working space around panels as "clear and extend from the grade, floor, or platform to the heigth required by 110.26(E).

As this pic shows, this install takes advantage of this "loophole" by putting the stairs to the basement directly under the panel.

- renosteinke

Top
Tools for Electricians:
#120278 - 04/04/05 08:49 PM Re: Working Space- Services- 220.26(A)3
chi spark Offline
Member

Registered: 01/06/04
Posts: 102
Loc: Chicago IL USA
Now I had a service upgrade in a NEC area, and the only spot available on the back wall of the house(local code) was over a crawlspace window well. I had to build a platform of treated lumber for the entire hole for access, not just 2' from the wall, but the entire hole(42"). Does that picture really utilize a loophole in the NEC? Wouldn't you need a railing on that "platform"? At 36" away from front, it looks like that meter is a bit high, 'cuz you're standing in the stairwell.

Top
#120279 - 04/05/05 01:05 AM Re: Working Space- Services- 220.26(A)3
SolarPowered Offline
Member

Registered: 07/05/04
Posts: 615
Loc: Palo Alto, CA, USA
It looks to me like the height of the topmost breaker handle is going to be just a little too high there.

Top