#109726 - 11/28/05 05:38 PM Some VERY Temporary Power
electure Offline

Member

Registered: 12/24/00
Posts: 4226
Loc: Fullerton, CA USA
 Quote:
Here are a couple of pictures of panels that are existing to the building, but the EC is using for temporary power. As an inspector, I would not permit this. During my inspection, I would tell them the correction had to be made IMMEDIATELY. I would give them a couple of hours, and I would come back to check this. It has been the normal routine in this area and now we are trying to stop this method. It is starting to occur.


Pierre Belarge






Top
2014 / 2011 NEC & Related Books and Study Guides
#109727 - 11/28/05 07:34 PM Re: Some VERY Temporary Power
Hemingray Offline
Member

Registered: 04/19/05
Posts: 195
Loc: Lehigh Acres, FL
yuck! who's responsible for this awful mess
_________________________
Cliff

Top
#109728 - 11/28/05 08:53 PM Re: Some VERY Temporary Power
dmattox Offline
Member

Registered: 10/20/04
Posts: 267
Loc: Anaheim, CA
I like how they wrap the wires around the copper water pipe for support.

Top
#109729 - 11/28/05 09:01 PM Re: Some VERY Temporary Power
royal12136 Offline
Member

Registered: 10/29/05
Posts: 20
Loc: Shasta Lake, CA USA
Hideous,
What runs through the piping? Is it legit to run piping over a panel like that?

Tim

Top
#109730 - 11/28/05 09:41 PM Re: Some VERY Temporary Power
Lostazhell Offline
Member

Registered: 02/21/04
Posts: 1248
Loc: Bakersfield, CA (Originally Or...
Those panels look like they had indigestion from Thanksgiving and hoarked out a rats nest with all the trimmings

Top
#109731 - 11/29/05 04:29 AM Re: Some VERY Temporary Power
pauluk Offline
Member

Registered: 08/11/01
Posts: 7693
Loc: Norfolk, England
Is that temporary Romex entering the top of the panel just threaded through the bare knockout with no protection?

Not that it seems like such a big deal looking at the way most of the other cables are just hanging there......

Top
#109732 - 11/29/05 06:29 AM Re: Some VERY Temporary Power
Ryan_J Offline
Moderator

Registered: 08/19/03
Posts: 1355
Loc: West Jordan, Utah, USA
 Quote:
Hideous,
What runs through the piping? Is it legit to run piping over a panel like that?
Tim


See 110.26(F)
_________________________
Ryan Jackson,
Salt Lake City

Top
#109733 - 11/29/05 10:31 AM Re: Some VERY Temporary Power
John Crighton Offline
Member

Registered: 05/16/05
Posts: 172
Loc: Southern California
I'll probably regret saying this...

What's the problem? This is temporary wiring for the convenience of the contractors. Who hasn't done something like this when it's needed? What matters is whether the final product meets code.

If you're going to complain that the temporary wiring isn't properly supported at the panel, then why stop there? Demand that the romex be nailed up and protected all the way back to the receptacles. What the heck, if it's commercial property, don't even let 'em use romex for temporary wiring at all -- demand MC or AC. Where do you draw the line?

The point is, I see nothing inherently unsafe about this practice. Anybody in the construction trades walking by these rats nests will give them wide berth.

The only problem I'd have is if the building is occupied and the area is accessible to tenants, in which case the panels should be closed up and the wires secured against accidental movement.

Now, how come phase C in the top picture is white, and if it's an existing panel, where's the conduit for the feeder???

Top
#109734 - 11/29/05 02:24 PM Re: Some VERY Temporary Power
PCBelarge Offline
Member

Registered: 06/08/03
Posts: 657
Loc: Dobbs Ferry, NY, USA
John
I hope you are kidding.
The reason I posted these pictures is because the practice you see is pretty common, but is deplorable. It is not professional or safe in any manner, and does not comform to many code requirements. Your response is pretty typical for contractors who have not learned the proper way to install electrical installations, whether temporary or permanent.

BTW: This work gets red tagged every time, and is considered hazardous, so I also make sure that it is corrected IMMEDIATELY.


A question to add to this post.
These installations are in dwellings. The installer leaves at night to go home. The homeowner has no lights, as during the day one of the circuits has been tripped during the construction. Would anyone feel comfortable with having the homeowner trying to reset one of these circuit breakers?

[This message has been edited by PCBelarge (edited 11-29-2005).]
_________________________
Pierre Belarge

Top
#109735 - 11/29/05 02:30 PM Re: Some VERY Temporary Power
PCBelarge Offline
Member

Registered: 06/08/03
Posts: 657
Loc: Dobbs Ferry, NY, USA
I forgot to answer about the plumbing pipe. In the picture it is difficult to tell, but the pipe is actually behind the panel.
And yes, this work is as bad as it looks.