The Electrical Contractor Network

ECN Electrical Forum
Discussion Forums for Electricians, Inspectors and Related Professionals

Books, Tools and Test Equipment for Electrical and Construction Trades

Topic Options
Rate This Topic
#104634 - 09/17/03 05:01 AM Mission Impossible! Electrician Was Blamed! He was there first!
Joe Tedesco Offline
Member

Registered: 10/07/00
Posts: 3325
Loc: Boston, Massachusetts USA


Mission Impossible! Electrician Was Blamed! He was there first!
_________________________
Joe Tedesco, NEC Consultant

Top
2014 / 2011 NEC & Related Books and Study Guides
#104635 - 09/17/03 07:39 AM Re: Mission Impossible! Electrician Was Blamed! He was there first!
mamills Offline
Member

Registered: 11/30/01
Posts: 739
Loc: Wharton, Texas, USA
I don't work in the trades, as the rest of you do. I guess you really don't have to, in order to recognize how utterly disrespectful this is. It shows no concern whatsoever for the electrician, the POCO meter reader, or the homeowner/apartment renter.

The plumber or heating contractor gets a big fat zero on this one, and ought to be cited .

Mike (mamills)

Top
#104636 - 09/17/03 09:43 AM Re: Mission Impossible! Electrician Was Blamed! He was there first!
ElectricAL Offline
Member

Registered: 10/10/01
Posts: 615
Loc: Minneapolis, MN USA
Some how I suspect that this is not in the side of an otherwise wide-open, expansive space. What's the rest of the description of situation?

The situations I've been involved with that resulted in 5 pounds being stuffed into a 3 pound bag have had a truly complicated set of constraints imposed by the physical configuration of the structure. What's the context?

Since the "electrician was blamed", were there plans that weren't followed when "he was there first"?

How much of this image is created by the foreshortening of the camera lens?
_________________________
Al Hildenbrand

Top
#104637 - 09/17/03 09:57 AM Re: Mission Impossible! Electrician Was Blamed! He was there first!
Joe Tedesco Offline
Member

Registered: 10/07/00
Posts: 3325
Loc: Boston, Massachusetts USA
Al: Here's the note that came with the images:

 Quote:
ENCLOSED ARE A COUPLE OF PHOTOS TAKEN AT A SITE WHERE WE WERE ASKED TO WIRE THREE NEW BOILERS IN A 5’6” x 6’ ROOM IN AN APARTMENT HOUSE.

PREVIOUS PLUMBING WORK AND THE NEW PLUMBING “SLIGHTLY” COMPROMISED 110.26.

THANKS,



The blamed comment was something I made up since it is often true.
_________________________
Joe Tedesco, NEC Consultant

Top
#104638 - 09/17/03 12:06 PM Re: Mission Impossible! Electrician Was Blamed! He was there first!
HotLine1 Offline

Member

Registered: 04/03/02
Posts: 6804
Loc: Brick, NJ USA
Based on the apparent age of the electrical equipment (FPE Panels) the electrical was there for a long time. The copper is and looks new, as the flue pipes.

The plumbing inspector would have a field day with this, IF it's an area that has inspections.

John

Edit:
Before someone else jumps on the bandwagon; they're Federal breakers, no need to reset, they never tripped.

John

[This message has been edited by HotLine1 (edited 09-17-2003).]
_________________________
John

Top
#104639 - 09/18/03 04:31 PM Re: Mission Impossible! Electrician Was Blamed! He was there first!
circuit man Offline
Member

Registered: 11/05/01
Posts: 287
Loc: saluda,s.c.
now where did you say you wanted those new boilers?

Top
#104640 - 09/18/03 06:14 PM Re: Mission Impossible! Electrician Was Blamed! He was there first!
ThinkGood Offline
Member

Registered: 08/07/02
Posts: 1084
Loc: Milwaukee, WI
Could the POCO disconnect the service [outside] for lack of access to the meter?

It appears that they just might have had a permit. The green kind, signed by the Treasurer of the US and the Secretary of the Treasury...

Top



ECN Electrical Forums - sponsored by Electrical Contractor Network - Electrical and Code Related Discussion for Electrical Contractors, Electricians, Inspectors, Instructors, Engineers and other related Professionals