Typical Scenario:

Monday morning's first stop was to inspect the Type NM-B cables and device boxes, etc., and fire alarm wiring located in the metal stud walls in a small men's clothing store.

Upon arrival the electrical inspector found the Sheetrock already up and taped.

What was the inspector's solution?
We had a GC in Reno that was fond of doing this sort of thing. Finally, one day the inspector poked a small hole in the wall, inserted a piece of wire, withdrew it....and Voila! No insulation!
Contractor ordered to take down rock in every house in developement for inspection. I think he was bankrupted by this- but he certainly knew better, but persisted in his 'cleverness.'
The last few inspectors I have dealt with require proof one way or another. All of them have accepted pictures of the work done, as long as the quality of the work could be seen, as well as the location. The inspectors were familiar with the quality of the work of the crews already. Otherwise you would have to show them, even if it meant removing the rock or chipping out concrete...
The sheetrock would have to be removed here.

Roger
Rip it down and show me [Linked Image]
If it's covered they are usually hiding something!!! So it's comming down here also
especially if it's a licenced contractor no excuse for *#@% like that
Gentlemen: I have been in the situation where I requested an inspection on Friday.
The following Friday I told the guys installing dry wall to wait until Wed. I again called for inspection that Fri afternoon. On Wed it still hadn't been inspected and got covered. Some of the dry wall came down for inspection, but I wasn't happy about it. Just how long do we hold up a job for an inspection?
The worst situation that I heard of was a pool contractor who jumped a bonding inspection. It wasn't the first time.

Needless to say, the whole concrete inground pool had to come out.

The pool contractor learned a costly lesson.

Wait, it is not worth it sometimes.


Dnk.......
And along this thread, what is the problem of rocking just one side, if rockers are in a hurry?


Dnk......
Here in NJ I have seen one side of walls sheetreocked on large commercial projects many times, the rockers aren't held up and have something to do but I imagine it is not the best thing for their effiency. But most of the time the game is all about how fast can they get the C of O and not how efficient the crew is.
It will come down here Also if both sides are covered!!! [Linked Image]
But I did just come from a comercial job that I allowed them to rock one side before rough frame inspection [Linked Image] laugh
Don't any of your AHJs have some sort of time limit, e.g. a rule which says they must attend within 72 hours or something otherwise they lose the authority to demand anything?