ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Increasing demand factors in residential
by gfretwell - 03/28/24 12:43 AM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
Do we need grounding?
by NORCAL - 03/19/24 05:11 PM
240V only in a home and NEC?
by dsk - 03/19/24 06:33 AM
Cordless Tools: The Obvious Question
by renosteinke - 03/14/24 08:05 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
1 members (Scott35), 260 guests, and 19 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#194168 05/13/10 08:59 PM
Joined: May 2010
Posts: 5
D
New Member
I am currently looking at a 50 or 140KW solar install. According to the Electrical Safety Authority (Ontario) anything over 10KW of generation tied to the grid requires a 'plan approval'. Has anyone been through a plan approval weather solar or not? They charge any hourly rate, but they were unable to tell me how long my project would take, any thoughts?

Joined: Apr 2002
Posts: 7,381
Likes: 7
Member
I do Plan Review here in NJ, solar, and everything else electrically. Sure would be nice to have an hourly rate! (LOL)

Plan review is part of the permit application & approval process, and there are no 'Plan Review Fees'. The only exception involves projects that are submitted without prior approvals (Zoning/Planing Board, etc) which are subject to a charge, based on 20% of the electrical permit fees.

Again, interesting information learned via ECN


John