ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
Do we need grounding?
by NORCAL - 03/19/24 05:11 PM
240V only in a home and NEC?
by dsk - 03/19/24 06:33 AM
Cordless Tools: The Obvious Question
by renosteinke - 03/14/24 08:05 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
0 members (), 260 guests, and 19 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#5411 11/18/01 06:41 PM
Joined: Nov 2001
Posts: 5
J
Junior Member
I have been involved in a telephone equipment addition that upped the power consumption to the point that the triplex burned off at the mast head. My question is "Can a visual scan of the entrance give a clue as to its capacity?" Where do the power company engineers get their specs?

#5412 11/18/01 10:47 PM
Joined: Aug 2001
Posts: 599
N
Member
Power Co. engineers, or planers as they are called here, get their “specs” from the engineered drawings done by a registered engineer. They look at what the actual demand will be, not the connected load, and size accordingly. They always tend to size to the low end to reduce cost. If you added a considerable amount of load to this facility you could have very well exceeded the capacity of the utilities feeder without exceeding the actual service equipment rating. Hard to tell without more info.