ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Safety at heights?
by gfretwell - 04/23/24 03:03 PM
Old low volt E10 sockets - supplier or alternative
by gfretwell - 04/21/24 11:20 AM
Do we need grounding?
by gfretwell - 04/06/24 08:32 PM
UL 508A SPACING
by tortuga - 03/30/24 07:39 PM
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
1 members (Scott35), 528 guests, and 48 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Page 2 of 3 1 2 3
Joined: Feb 2002
Posts: 36
3
Member
Yeah, Resqcap...Schedule 40 PVC and I have no problem with 2"nipples or straight runs. Even the NEC table only shows a max. of two #4/0 RHW. One 90 is verticle, the other horizontal, both are buried leading into the control room....about 150-160 feet underground and an additional 75 feet up into the overhead tray and over into my distribution panels. We will see.....I'll keep you posted on how it goes.

Joined: Nov 2000
Posts: 2,148
R
Member
3rd degree,
I agree that the Table C10 says that only2 4/0 RHWs fit in a 2" schedule 40 PVC conduit, it also says that 3 4/0 THWs fit and 4 4/0 THWNs or XHHWs fit. With the proper equipment I don't see any problem other than the pull rope and or conductors cutting through the inside of the 90s. If this happens the conducotrs will be damaged.
Don(resqcapt19)


Don(resqcapt19)
Joined: Aug 2001
Posts: 599
N
Member
Don,
Mule tape is used by datacom people allot. I don't remember the exact material it's made of but it is smooth and flat with footage numbers stamped on it. I think its nylon. I have found it works well on small and medium size feeder pulls. It does not cut into PVC 90's. If I find a link or manufacturer I'll post back with it.

Joined: Dec 2000
Posts: 4,294
Member
Are you also including the #4 EGC in your calcs for conduit size? Doesn't it become 2-1/2"?

[This message has been edited by electure (edited 02-09-2002).]

Joined: Nov 2000
Posts: 2,148
R
Member
Electure,
I didn't include an EGC. I see that this is after the service disconnect so an EGC required and you are correct that when the #4 EGC is added a 2 1/2" conduit is requried.
Good catch!!
Don(resqcapt19)


Don(resqcapt19)
Joined: Feb 2002
Posts: 36
3
Member
Like I said, tommorrow should prove interesting...........

A
Anonymous
Unregistered
I guess you would be referring to me and my fellow engineers. I woudl agree that a lot of engineers need to have field experience before entering into any job requiring design. I am very glad that I am still getting my field trainging while earning my degree. I have looked at designs from professors and fellow students that are almost impossible to do in the real world. The trouble always comes from the lack of field experience.

Joined: Feb 2002
Posts: 36
3
Member
Electure, overheads are out of the question in a switchyard....EVERYTHING is buried in PVC (except for the high voltage transmission lines). I installed the disconnect about 20' below some comparatively small 38KV potential transformers....you get the picture.

Joined: Feb 2002
Posts: 36
3
Member
Cool........we made our run today, a HARD pull, a tackle and a bucket of soap, but otherwise OK. Actually, we ended up pulling THW instead of RHW and only three 4/0's instead of four(2 hots & neutral). We will derive our ground somewhere else-son't ask, there are miles of grounded grid electrodes in a switchyard and the EGC will come into an overhead in an opposite direction than where I took our service-it gets complicated but the entire yard is fairly "flat" as a result). Really though, I don't think we could have negotiated that last PVC elbow if we had to pull four in that damn 2".

Joined: Aug 2001
Posts: 599
N
Member
Quote
We will derive our ground somewhere else-son't ask, there are miles of grounded grid electrodes in a switchyard and the EGC will come into an overhead in an opposite direction than where I took our service-it gets
We did a small power plant last summer that I spent a few weekends at. The grounding (bonding) scheme was similar. Just tap into the ground grid anywhere. I did then and still do think it is a violation of 250.134(B). I don't understand why things suddenly change just because your we are inside a substation or power plant.

Page 2 of 3 1 2 3

Link Copied to Clipboard
Powered by UBB.threads™ PHP Forum Software 7.7.5