ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Safety at heights?
by gfretwell - 04/23/24 03:03 PM
Old low volt E10 sockets - supplier or alternative
by gfretwell - 04/21/24 11:20 AM
Do we need grounding?
by gfretwell - 04/06/24 08:32 PM
UL 508A SPACING
by tortuga - 03/30/24 07:39 PM
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
1 members (Scott35), 235 guests, and 27 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Page 2 of 2 1 2
#42877 11/01/04 04:29 PM
Joined: Nov 2000
Posts: 2,236
Likes: 1
Member
Tom, et al,

The service consists of a 320A disconnect (I think, maybe a 400A) feeding a 320A Meterbase (no CTs). This directly feeds a 75KVA Dry type Xformer that feeds a 225A 120/208 panel, which will be totally redone with the Xformer being fed from the new 480V power panel.

Not all the machines can run on 480V, the moulder will have to be 240V Three Phase with its own Xformer, I suppose.

Heck, just to run pipe and wire to these machines is going to be major, I really don't have the resources and he's offering "help"... (hoo boy - smacking self in forehead)...

The layout will require a boom lift, sissors won't reach most of the places, specifically the switchgear area.

He'll be buying the materials, so I'll lose mark-up, and I'll end up doing the brain-work at an undetermined price (read > free)...

Yes this is beginning to smell of $1000 bills going up in smoke...

(post edit)

Oh yes, he claims very few, if any, machines will be running at the same time, but one good jolt of trying to meet some deadline will probably find the service to be inadequate. Then he'll be mad at me...

Conversely, if he never has a problem with my "over-designed" system, then this merely proves that it was unneccesary to make it so large...

I'm beginning to hate this business.

[Linked Image]

[This message has been edited by sparky66wv (edited 11-01-2004).]


-Virgil
Residential/Commercial Inspector
5 Star Inspections
Member IAEI
#42878 11/01/04 05:11 PM
Joined: Jan 2002
Posts: 1,457
E
Member
Run, Run, don't look back, just run.

#42879 11/01/04 07:24 PM
Joined: Jan 2001
Posts: 1,044
Tom Offline
Member
Virgil,

If you interlock the machines so that they cannot run at the same time or exceed the service capacity, then you might get by with the existing service. However, you could still talk to the Allegheny & install another mast & meter & service disconnect.

Anyway, you know where to come for advice. Might be nice to have a little work lined up for winter.

Also, I agree that this business is not near as much fun as it was 20 years ago. [Linked Image] [Linked Image] [Linked Image]


Few things are harder to put up with than the annoyance of a good example.
#42880 11/04/04 11:17 AM
Joined: Nov 2000
Posts: 2,236
Likes: 1
Member
I bailed.


-Virgil
Residential/Commercial Inspector
5 Star Inspections
Member IAEI
#42881 11/04/04 12:01 PM
Joined: Oct 2000
Posts: 4,116
Likes: 4
Member
Quote
one good jolt of trying to meet some deadline will probably find the service to be inadequate. Then he'll be mad at me...

Conversely, if he never has a problem with my "over-designed" system, then this merely proves that it was unneccesary to make it so large...
truer words were never spoken. I'm glad to hear that you bailed.

Hey, don't be such a stranger!

[Linked Image]


Bill