ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
UL 508A SPACING
by ale348 - 03/29/24 01:09 AM
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
Do we need grounding?
by NORCAL - 03/19/24 05:11 PM
240V only in a home and NEC?
by dsk - 03/19/24 06:33 AM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
1 members (ale348), 302 guests, and 14 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Joined: Dec 2002
Posts: 308
E
Edward Offline OP
Member
I have to bid on a complete rewire and services and subpanel upgrades for two complexes. One is a 3 single unit complex and other is a 4 single unit complex. Each individual unit is about 800sqft.
My questios is can i treat this as one main 200Amp disconnect with 3 or 4 60 amp individual mains?
If not can i use the standard load calculation for each unit and add it all up to see what my main will be?

PS. It is all gas heater and cooking appliance. One laundry unit for both buildings.

Merci
Edward


Thanks
Edward
Joined: Dec 2003
Posts: 751
E
Member
You have to do both.
Each individual unit must have it's feeder calculated, and the building must have it's size calculated for the entire building loads.

Earl


Earl