per sq. ft bid is a start. what i always get hung up on is the lighting, i'll usually ask for a lighting layout, even refer to a good lighting shop that will do the work for the sale of the lighting package ( this works great if you can bring it together) then a per stop $ is for real. changes suck, let's face it, indecision should not be at our expense right? and people tend to jab you with the T&M---your here, it's cheap line. well it's aggravation, so i contract extra's @ T&M WITH an added per stop premium
Oh yeah, Steve (sparky) tried to warn me...Others have told me to be a tad greedy, yet still competitive. Imagine my suprise when 4 sparky's show up @ the genny store jawbonnin' rates an' i'm the low boy in town !
I should heed my own advice....