ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Increasing demand factors in residential
by gfretwell - 03/28/24 12:43 AM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
Do we need grounding?
by NORCAL - 03/19/24 05:11 PM
240V only in a home and NEC?
by dsk - 03/19/24 06:33 AM
Cordless Tools: The Obvious Question
by renosteinke - 03/14/24 08:05 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
1 members (Scott35), 278 guests, and 16 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#30717 10/26/03 01:14 PM
Joined: Mar 2003
Posts: 10
T
Member
I have a MCC feeding a 600 amp 277/480 4 wire MCC. I'm using parallel 500mcm for the phases but there is no actuall load on the neutral so can I get away with no neutral? My concern is that the blue prints list it as 4 wire so do you think they want a neutral pulled for future use maybee?

Any info appreciated.

Joined: Jun 2001
Posts: 642
N
Member
Tim
Where is this MCC getting it's control power from?
If the plans and specs call out 4 wire, I would install a full size neutral. You cannot know what is planned for the future unless all the MCC buckets are used now.


ed
Joined: Jan 2003
Posts: 4,391
I
Moderator
If the plans called for a four wire feeder to this MCC and you bid it and won it with that requirement you should install it.

Putting aside that it is the right thing to do, if after you leave the job they need that neutral who do you think will pay for it to be installed?


Bob Badger
Construction & Maintenance Electrician
Massachusetts
Joined: Mar 2003
Posts: 10
T
Member
One bucket of the mcc is feeding a transformer which in turn id feeding a 120/208 panel. This panel is feeding two controll panels for all my controll wiring.
Each bucket of the mcc has a TRF for the coils within it.

I did not bid the job but the nuetral was included in the bid so IMO it should be included but my superiors think different.

This post is mostly meant to justify my thinking, I wanted to make sure I wasnt missing something.

Joined: Aug 2003
Posts: 1,374
R
Moderator
I would send an RFI to the engineer and get a CCD on paper to cover your back.


Ryan Jackson,
Salt Lake City
Joined: Feb 2003
Posts: 198
Z
Member
Tim,- Was an equip. gnd. pulled in?, since someone is trying to cut corners on your job?


Shoot first, apologize later.....maybe
Joined: Mar 2003
Posts: 10
T
Member
Yes a equipment ground will be pulled in

Joined: Aug 2003
Posts: 123
P
Member
I feel it is up to the owner.
Now cost vs. later. Explain the cost at a later date.
If he wants to save money at this point, he may want to.
I also agree with paper from the engineer, CYA.