ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Safety at heights?
by gfretwell - 04/22/24 10:36 AM
Old low volt E10 sockets - supplier or alternative
by gfretwell - 04/21/24 11:20 AM
Do we need grounding?
by gfretwell - 04/06/24 08:32 PM
UL 508A SPACING
by tortuga - 03/30/24 07:39 PM
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
0 members (), 211 guests, and 10 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Page 2 of 2 1 2
Joined: Nov 2000
Posts: 2,148
R
Member
John,
Was the ground fault trip setting ever set after the main was installed? They often come from the factory set at the lowest setting and it is not uncommon to have the main trip on ground fault without tripping the branch breaker when the main is left at the factory setting.


Don(resqcapt19)
Joined: Apr 2002
Posts: 7,381
Likes: 7
Member
The main was tested and 'set' by a factory tech from Siemens after initial install & energization. Factory tech returned after this incident & checked; all was within previously set range.


John