It’s real Simple, make one in Excel, or Word and copy it over and over. Use one from a GC as a template.
RFI- 001
TO: Spaw Glass Construction
Attention: Joe Blow
FROM: Big Electric
Contact: (insert your name here)
Regarding: Missing circuits for RTUs
Ref: Plan pages E2.1 and M2.1
Problem:
Plan page M2.1 Shows 4 AHU and 4 RTUs.
Plan page E2.1 does not show these units or any associated circuiting.
Solution:
Please provide circuiting, for these units.
Will there be a cost increase associated with this RFI?: Yes
Will there be a schedule impact associated with this RFI?: Yes
Response requested by: 1 Week
Response: (leave a large space for a written response.)