ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Do we need grounding?
by gfretwell - 04/06/24 08:32 PM
UL 508A SPACING
by tortuga - 03/30/24 07:39 PM
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
0 members (), 345 guests, and 27 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#157114 08/17/05 08:46 PM
Joined: Jan 2005
Posts: 5,445
Likes: 3
Cat Servant
Member
You're looking at the plans for a job, and you see something has been overlooked- or just won't work as drawn.

Do you tell this to the customer now- or do you wait until you get the job, then put in fo a change order? Or- just do what you were told, and let them figure it out?

Latest Estimating Cost Guides & Software:
Joined: Feb 2005
Posts: 219
S
Member
John
Everything up front, unless...... the guy's your bidding aren't asking the same questions. In that case bid it flat and pick up the "extra"

On competive bids you usually only have until the last two weeks to get your RFI's answerd. If you get them in in time the Architect will send out addendum's reflecting the changes so all bids will be equal.

Rob

Joined: May 2005
Posts: 706
T
Member
It depends what kind of plan I have and how much time I want to spend on it. For an existing client I bring it to their attention and include it in the Contract Proposal. I make a note that says something like "Bid to print with the following additions".

For a price-shopper with a sketch, I add a note that says something like "Bid to print. Plans should be submitted to the local Building Department for Permit and approval."

Dave

Joined: Apr 2002
Posts: 914
E
Member
It depeds on the situation, but I tend to point these things out. I think it makes my proposal look more complete if I point out mistakes and the fact that I considered them before starting the project. A customer might pay a considerable amount more if they know I'm not going to hit them with change orders.

I personally don't like change orders. I would never submit a low bid to get a job thinking "I'll just make it up on change orders". My regular customers know this and often don't even get competing bids.

Joined: Jan 2003
Posts: 1,429
L
LK Offline
Member
"A customer might pay a considerable amount more if they know I'm not going to hit them with change orders."

___________________________________________

Yes they do, and they usually become your best customers, bringing their attention to errors, and items that were missed, puts you in a much better light, for bringing in the job on, or under budget.