ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Do we need grounding?
by gfretwell - 04/06/24 08:32 PM
UL 508A SPACING
by tortuga - 03/30/24 07:39 PM
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
0 members (), 390 guests, and 14 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#13355 08/31/02 08:44 PM
Joined: Apr 2001
Posts: 449
F
Fred Offline OP
Member
I tried a new(at least to me)method of pulling in EMT yesterday. I had a 150' run of 2" EMT that I had to pull (3) 1/0 and a #2 THHN through with 3 90º turns. I had already pulled a 5/16" rope in to pull the conductors with. I bought a 2"x4"x8" sponge at the hardware store and cut into 2" strips. I loop-knotted the pulling rope about 2' and again at 4' from the pulling head and tied the pieces of the sponge in. I then gooped about a quart of Yellow 77 into the conduit. We pulled/pushed the whole run by hand in about 10 minutes! The first sponge came out the end black and the second one came out dragging about a 1/2 pint of the 77. It was the easiest 3/0 pull I have ever done and the least messy. I know I'm not the first one to do this but I don't remember seeing it here before and thought it was worth sharing.

#13356 08/31/02 11:25 PM
Joined: Apr 2001
Posts: 507
G
Member
thanks fred, I'll have to try that.

GJ