Here's a (name removed) utility job - NOTE 13kv riser cables up against streetlight lumiare.
Jay Anderson (submitted via Joe Tedesco)
|
|
|
|
Joined: May 2003
Posts: 2,876
Member
|
Ok my line or outside experiance is limited.... But is the pole too short? Looks like 54'? if thats a 40' there next to it. Secondary and street lighting side too high? Both? Isn't there a rule for seperation of so many feet? Any of the linemen out there got comments for that?
Am sure they should not be wrapped around aech other like that...
Mark Heller "Well - I oughta....." -Jackie Gleason
|
|
|
|
Joined: Jun 2004
Posts: 220
Member
|
doesn't look like there is any type of bushing on that riser.
|
|
|
|
Joined: Oct 2002
Posts: 482
Member
|
Who has to service that cobra-head light fixture?
Not me...
|
|
|
|
Joined: Apr 2002
Posts: 2,527
Moderator
|
Utility systems are often designed and installed under the National Electrical Safety Code, published by IEEE. [In California, the document is General Order 95 for overhead systems, at ]www.cpuc.ca.gov/Published/Graphics/13352.PDF]
|
|
|