ECN Electrical Forum - Discussion Forums for Electricians, Inspectors and Related Professionals
ECN Shout Chat
ShoutChat
Recent Posts
Do we need grounding?
by gfretwell - 04/06/24 08:32 PM
UL 508A SPACING
by tortuga - 03/30/24 07:39 PM
Increasing demand factors in residential
by tortuga - 03/28/24 05:57 PM
Portable generator question
by Steve Miller - 03/19/24 08:50 PM
240V only in a home and NEC?
by dsk - 03/19/24 06:33 AM
New in the Gallery:
This is a new one
This is a new one
by timmp, September 24
Few pics I found
Few pics I found
by timmp, August 15
Who's Online Now
0 members (), 220 guests, and 12 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
#101171 02/14/07 12:22 PM
Joined: Sep 2004
Posts: 138
R
royta Offline OP
Member
I've always been confused on whether I need a main breaker for a sub-panel.

Situation 1 - Residential main service with a feeder breaker feeding sub-panel mounted within or on home. Is there a situation when the sub-panel needs a main?

Situation 2 - Residential main service with a feeder breaker feeding sub-panel mounted on seperate structure or somewhere else on property. Sub-panel only needs a main IF there are more than six breaker handles (twin counts as two handles), correct?

Situation 3 - 400A residential main service with first 200A main supplying the built-in distribution. Second 200A main feeding 20/40 sub-panel located on other side of house. Sub-panel has conduit provisions to supply future sub-panels located on other structures or areas of property.

Situation 4 - Commercial main service on exterior of building. Individual feeder (main) breakers feeding sub-panels located in each commercial suite. Every sub-panel I've ever seen in these situations always has a main breaker.

[This message has been edited by royta (edited 02-14-2007).]

Stay up to Code with the Latest NEC:


>> 2023 NEC & Related Reference & Exam Prep
2023 NEC & Related Reference & Study Guides

Pass Your Exam the FIRST TIME with the Latest NEC & Exam Prep

>> 2020 NEC & Related Reference & Study Guides
 

#101172 02/14/07 12:49 PM
Joined: Jan 2001
Posts: 1,044
Tom Offline
Member
1. Not needed

2. Needed if six disconnects are exceeded. A 2 pole breaker is one breaker. If by twin you mean a breaker with two separate handles, then the twin counts as two.

3. Not needed

4. Not needed