Joe,

Let me add 2 cents here. I was given a set of prints to plan review. I failed the print and said that I wanted more information on the generator and the grounding of the generator. The engineering company called me and asked why I failed the plan. I told them that I just wanted to inspect the new generator (gen) and to make sure that it was installed as per the engineer's design and to make sure that it all met the NEC. The engineer told me that the contractor was to submit a plan as to how the generator (gen) was to be wired and to make sure that I liked the way the generator was to be wired. I told the engineer that neithe rthe contractor nor I was to be designing this Gen. HE was the person to be designing it, and that I would review his plan to make sure that it met NEC. I couldn't get that through his head. I told the contractor that I didn't want him to design anything, the EE was the man to sign off on the design.