In reply to George's comments:
"You either follow the prescription or you have an engineer deviate from the prescription and stamp the plans.

Conduit fill is a prescription. An engineer can deviate from it."

This does not apply in NJ. (period)

UCC 5:23 et al is our 'Code'; NEC is slightly ammended and adopted as part of the UCC>

John


John