It's a requirement for JCP&L in certain circumstances. Typically if the transformer bank serves more than one service. They want to be able to shut down just one service if they need to work on the meter. I don't fully understand it, but they want it. We had to do it in Red Bank as far back as 4 yrs ago.

As for who pays - tough one.

Who designed the service?